1320 S GENESEE AVE 90019

Certificate Information: 1320 S GENESEE AVE 90019

Application / Permit
21014-10000-03044
Plan Check / Job No.
B21LA11348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
EXTEND REAR OF (E) GARAGE. NO CHANGE IN HEIGHT.
Permit Issued
Issued on 9/17/2021
Issuing Office
Current Status
CofO Issued on 10/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/22/2021 LAWRENCE QUIRANTE
Corrections Issued 6/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/11/2021 JESSE JIMENEZ
Applicant returned to address corrections 8/25/2021 RAMA DABADGE
Plan Check Approved 9/8/2021 LAWRENCE QUIRANTE
Issued 9/17/2021 APPLICANT
Building Plans Picked Up 9/29/2021 APPLICANT
CofO in Progress 7/27/2022 JOSE AVILA
No Progress 8/26/2022 JOSE AVILA
CofO in Progress 8/26/2022 JOSE AVILA
Permit Finaled 10/12/2022 DEROLD HAUFF
CofO Issued 10/12/2022 DEROLD HAUFF
Permit Finaled 10/12/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/8/2021 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 7/9/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2021 Partial Approval JOSE AVILA
METHANE-Barrier 10/20/2021 Approved JOSE AVILA
METHANE-Subgrade 10/20/2021 Approved JOSE AVILA
Deputy Drilled-In Anchors 10/22/2021 Approved JOSE AVILA
Footing/Foundation/Slab 10/26/2021 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 10/28/2021 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 10/29/2021 Approved JOSE AVILA
Deputy Drilled-In Anchors 11/1/2021 Conditional Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Approved JOSE AVILA
METHANE-Rough 2/18/2022 Approved JOSE AVILA
Wood Frame 2/18/2022 Corrections Issued JOSE AVILA
Deputy Wood Construction 2/23/2022 Conditional Approval JOSE AVILA
Interior/Exterior Lathing 3/8/2022 Partial Approval JOSE AVILA
Interior/Exterior Lathing 5/4/2022 Approved JOSE AVILA
Final 6/27/2022 Partial Inspection JOSE AVILA
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 6/27/2022 Approved JOSE AVILA
Wood Frame 6/27/2022 Approved JOSE AVILA
Final 7/8/2022 Corrections Issued JOSE AVILA
Final 7/26/2022 OK to Issue CofO JOSE AVILA