1320 S GENESEE AVE 90019
Certificate Information: 1320 S GENESEE AVE 90019
- Application / Permit
- 21014-10000-03044
- Plan Check / Job No.
- B21LA11348
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- EXTEND REAR OF (E) GARAGE. NO CHANGE IN HEIGHT.
- Permit Issued
- Issued on 9/17/2021
- Issuing Office
- Current Status
- CofO Issued on 10/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/23/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 8/11/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 8/25/2021 | RAMA DABADGE |
| Plan Check Approved | 9/8/2021 | LAWRENCE QUIRANTE |
| Issued | 9/17/2021 | APPLICANT |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| CofO in Progress | 7/27/2022 | JOSE AVILA |
| No Progress | 8/26/2022 | JOSE AVILA |
| CofO in Progress | 8/26/2022 | JOSE AVILA |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
| CofO Issued | 10/12/2022 | DEROLD HAUFF |
| Permit Finaled | 10/12/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2021 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 7/9/2021 | CECILIO NAVARRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/20/2021 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 10/20/2021 | Approved | JOSE AVILA |
| METHANE-Subgrade | 10/20/2021 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 10/22/2021 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 10/26/2021 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 10/28/2021 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 10/29/2021 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 11/1/2021 | Conditional Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2021 | Approved | JOSE AVILA |
| METHANE-Rough | 2/18/2022 | Approved | JOSE AVILA |
| Wood Frame | 2/18/2022 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 2/23/2022 | Conditional Approval | JOSE AVILA |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | JOSE AVILA |
| Interior/Exterior Lathing | 5/4/2022 | Approved | JOSE AVILA |
| Final | 6/27/2022 | Partial Inspection | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 6/27/2022 | Approved | JOSE AVILA |
| Wood Frame | 6/27/2022 | Approved | JOSE AVILA |
| Final | 7/8/2022 | Corrections Issued | JOSE AVILA |
| Final | 7/26/2022 | OK to Issue CofO | JOSE AVILA |