3052 W GLENHURST AVE 90039
Certificate Information: 3052 W GLENHURST AVE 90039
- Application / Permit
- 21014-10000-03039
- Plan Check / Job No.
- B21LA11341
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY ADDITION TO (E) SFD FOR NEW LAUNDRY AND BATHROOM
- Permit Issued
- Issued on 10/31/2021
- Issuing Office
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/22/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/8/2021 | RAHEL BEYENE |
| Plan Check Approved | 10/8/2021 | ADAM HEGAZI |
| Issued | 10/31/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 11/3/2022 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
| CofO Issued | 11/9/2022 | DEROLD HAUFF |
| Permit Finaled | 11/9/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/22/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/22/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2021 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 9/28/2021 | JEFFREY BULL |
Contact Information
| Contractor | New Era Contractors Ltd; Lic. No.: 939229-B | 18411 ELAINE AVE ARTESIA, CA 90701 |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 1/12/2022 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/11/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/30/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/30/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/30/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Sewer | 3/31/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/19/2022 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/10/2022 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/10/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 6/14/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/22/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 8/22/2022 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 8/22/2022 | Partial Approval | HAMIK HARTOUNIAN |
| Insulation | 8/26/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/6/2022 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/4/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 10/12/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/12/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/12/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/12/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/12/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/20/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/20/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 10/20/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/20/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 10/27/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/27/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 10/27/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/27/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 11/3/2022 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/3/2022 | Approved | HAMIK HARTOUNIAN |