4961 W CROMWELL AVE 90027
Certificate Information: 4961 W CROMWELL AVE 90027
- Application / Permit
- 21014-10000-03022
- Plan Check / Job No.
- B21LA11253
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) NURSERIES STRUCTURE ADDITION AND INTERIOR REMODEL TO (E) 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 8/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | DANIEL YIP |
| Corrections Issued | 7/12/2021 | DANIEL YIP |
| Quality Review Completed | 7/23/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 8/18/2021 | DANIEL YIP |
| Applicant returned to address corrections | 12/8/2021 | DANIEL YIP |
| Plan Check Approved | 12/22/2021 | DANIEL YIP |
| Issued | 1/6/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 8/14/2023 | JOSEPH MCGARRY |
| Permit Finaled | 8/17/2023 | RONALD MYRICK |
| CofO Issued | 8/17/2023 | RONALD MYRICK |
| Permit Finaled | 8/17/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/3/2021 | THOMAS LANG |
| ZA Case | Cleared | 8/10/2021 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | THOMAS LANG |
| GPI Written Notices | Cleared | 12/8/2021 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 12/8/2021 | DANIEL YIP |
Contact Information
| Architect | Herrero,, Andre; Lic. No.: C38434 | 6253 HOLLY MONT DR LOS ANGELES, CA 90068 |
| Contractor | Vallernaud Construction Inc; Lic. No.: 1025929-B | 11826 ALLASEBA DR LOS ANGELES, CA 90066 |
| Engineer | Khanjian,, Hovik J; Lic. No.: C51609 | 326 S. SPARKS STREET BURBANK, CA 91506 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 5/20/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Steel/Welding | 5/31/2022 | Conditional Approval | ADAM ESCOTO |
| ELECTRICAL-Rough | 7/22/2022 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/22/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 7/25/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/17/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 8/17/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/17/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/22/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 8/22/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 8/22/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/25/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/25/2022 | Partial Approval | JOSEPH MCGARRY |
| HVAC-Rough | 8/25/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/30/2022 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 8/30/2022 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/30/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 8/30/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 9/9/2022 | Approved | JOSEPH MCGARRY |
| Gas Test | 9/9/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 9/9/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 10/11/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/11/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 10/24/2022 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 10/31/2022 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Final | 4/6/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 4/6/2023 | Approved | JOSEPH MCGARRY |
| Gas Test | 4/13/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 4/13/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Final | 6/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Green Building Final | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Smoke Detectors | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Special/Order Compliance | 7/11/2023 | Approved | JOSEPH MCGARRY |
| Final | 8/11/2023 | OK to Issue CofO | JOSEPH MCGARRY |