13274 W PARKLAND CIR 91342

Certificate Information: 13274 W PARKLAND CIR 91342

Application / Permit
21014-10000-03014
Plan Check / Job No.
B21LA11238
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW GROUND FLOOR PATIO ADDITION AND 2-STORY ADDITION (663 SF) TO EXISTING 2-STORY SFD.
Permit Issued
Issued on 6/1/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 VIVIAN LAO
Corrections Issued 7/30/2021 VIVIAN LAO
Quality Review Completed 8/10/2021 MICHAEL PEREZ
Building Plans Picked Up 8/12/2021 APPLICANT
Applicant returned to address corrections 5/17/2022 VIVIAN LAO
Plan Check Approved 5/18/2022 VIVIAN LAO
Issued 6/1/2022 APPLICANT
CofO in Progress 11/15/2023 ROBERT GOLD
Permit Finaled 11/25/2023 RUBEN SALAS
CofO Issued 11/25/2023 RUBEN SALAS
Permit Finaled 11/25/2023 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/15/2021 PATRICK MISCHLICH
Eng Process Fee Ord 176,300 Cleared 1/15/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/15/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/21/2022 TA ANH
Roof/Waste drainage to street Cleared 1/28/2022 ABDULLAH SADOZAI
GPI Written Notices Cleared 4/8/2022 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/27/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 7/1/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/7/2022 Approved ARAM AVEDISIAN
Wood Frame 9/7/2022 Corrections Issued ARAM AVEDISIAN
Deputy Wood Construction 9/9/2022 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 9/12/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/5/2022 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 10/7/2022 Approved ARAM AVEDISIAN
HVAC-Rough 10/7/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 10/7/2022 Partial Approval ARAM AVEDISIAN
Green Building Rough 10/12/2022 Approved ARAM AVEDISIAN
Insulation 10/12/2022 Approved ARAM AVEDISIAN
Drywall Nailing 11/4/2022 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/4/2022 Approved MATTHEW NELSON
Shower Pan 11/4/2022 Approved MATTHEW NELSON
Final 5/26/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 5/26/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 5/26/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 8/16/2023 OK to Issue CofO ROBERT GOLD
Green Building Final 8/16/2023 Approved ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 8/16/2023 SGSOV Approved ROBERT GOLD
Smoke Detectors 8/16/2023 Approved ROBERT GOLD