10632 N HASKELL AVE 91344

Certificate Information: 10632 N HASKELL AVE 91344

Application / Permit
21014-10000-03010
Plan Check / Job No.
B21LA11225
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
TWO CAR GARAGE TO BE CONVERT TO AN ADU WITH ADDITION PER CA GOVT. CODE 65852.2 (e)(1)(B) AND LAMC 12.22A.33 (c)-(d),(g).
Permit Issued
Issued on 1/26/2022
Issuing Office
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 MAHNAZ NOURHASHEMI
Corrections Issued 7/27/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 8/5/2021 JASON HEALEY
Building Plans Picked Up 8/6/2021 APPLICANT
Plan Check Approved 1/26/2022 MAHNAZ NOURHASHEMI
Issued 1/26/2022 APPLICANT
CofO in Progress 12/4/2023 JAVIER RAMOS JR
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/30/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 8/3/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/1/2021 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 11/2/2021 KURT CORRAL
Low Impact Development Cleared 1/10/2022 TA ANH
Roof/Waste drainage to street Cleared 1/12/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2022 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 4/25/2022 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/4/2022 Not Ready for Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 5/4/2022 Not Ready for Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 5/9/2022 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/9/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 6/9/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/16/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/16/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/16/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 6/16/2022 Approved JAVIER RAMOS JR
MERV13>=Rough 6/16/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 6/16/2022 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 6/23/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/23/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/23/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 6/23/2022 Corrections Issued JAVIER RAMOS JR
Shower Pan 6/24/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/5/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 9/8/2022 Approved JAVIER RAMOS JR
Green Building Rough 9/8/2022 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 9/8/2022 Approved JAVIER RAMOS JR
Insulation 9/9/2022 Corrections Issued JAVIER RAMOS JR
Drywall Nailing 9/12/2022 Approved JAVIER RAMOS JR
Insulation 9/12/2022 Approved JAVIER RAMOS JR
ELECTRICAL-Final 10/12/2022 Not Ready for Inspection JAVIER RAMOS JR
Gas Test 10/12/2022 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 10/12/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 10/12/2022 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Not Ready JAVIER RAMOS JR
ELECTRICAL-Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 1/5/2023 Approved CHRISTOPHER DELLEFIELD
Gas Test 1/5/2023 Approved CHRISTOPHER DELLEFIELD
Green Building Final 1/5/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 1/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 1/5/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 1/5/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 1/5/2023 Approved CHRISTOPHER DELLEFIELD
Final 8/29/2023 No Access for Inspection JACK KARGODORIAN
Green Building Final 8/29/2023 No Access for Inspection JACK KARGODORIAN
MERV13>=Final 8/29/2023 No Access for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 8/29/2023 SGSOV Not Ready JACK KARGODORIAN
Final 10/13/2023 Corrections Issued ROBERT GOLD
Green Building Final 10/13/2023 Not Ready for Inspection ROBERT GOLD
MERV13>=Final 10/13/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Not Ready ROBERT GOLD
Service/Power Release 10/13/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 12/4/2023 Approved JAVIER RAMOS JR
Final 12/4/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 12/4/2023 Approved JAVIER RAMOS JR
HVAC-Final 12/4/2023 Approved JAVIER RAMOS JR
MERV13>=Final 12/4/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 12/4/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved JAVIER RAMOS JR