3885 S 3RD AVE 90008
Certificate Information: 3885 S 3RD AVE 90008
- Application / Permit
- 21014-10000-02995
- Plan Check / Job No.
- B21LA11160
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE W/ ADDITION TO 20'X21'-3" ADU 404 SF PER 12.22 A.33(C) & (D). CONSTRUCTION BY WFPP. 2 OF 2
- Permit Issued
- Issued on 1/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 8/2/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 8/12/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 10/6/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 10/12/2021 | CHUNG-WEN CHUANG |
| Plan Check Approved | 1/6/2022 | CHUNG-WEN CHUANG |
| Issued | 1/14/2022 | APPLICANT |
| Building Plans Picked Up | 1/20/2022 | APPLICANT |
| CofO in Progress | 10/4/2022 | ANTHONY EGSON |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
| CofO Issued | 12/15/2022 | DEROLD HAUFF |
| Permit Finaled | 12/15/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/25/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 10/8/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 12/8/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 12/28/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 1/28/2022 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 2/24/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 3/10/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 3/21/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/25/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/25/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 6/1/2022 | Approved | ANTHONY EGSON |
| Sewer | 6/6/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/7/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/9/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 6/10/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 6/21/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/21/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/28/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| Final | 9/15/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 9/15/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/15/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/15/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/15/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/3/2022 | Approved | ANTHONY EGSON |
| Final | 10/3/2022 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 10/3/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/3/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 10/3/2022 | Approved | ANTHONY EGSON |