3883 S 3RD AVE 90008

Certificate Information: 3883 S 3RD AVE 90008

Application / Permit
21014-10000-02994
Plan Check / Job No.
B21LA11160
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
23'-3"X25'-6" 1-STORY REAR ADDITION 593 SF AND FRONT ADDITION 71 SF (TOTAL ADDITION=664 SF) TO (E) 1-STORY SFD AND REMODEL. 1 OF 2
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 10/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 CHUNG-WEN CHUANG
Corrections Issued 8/2/2021 CHUNG-WEN CHUANG
Quality Review Completed 8/12/2021 ALLEN MANALANSAN
Applicant returned to address corrections 10/6/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 10/12/2021 CHUNG-WEN CHUANG
Plan Check Approved 1/6/2022 CHUNG-WEN CHUANG
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/20/2022 APPLICANT
CofO in Progress 10/4/2022 ANTHONY EGSON
Permit Finaled 10/26/2022 DEROLD HAUFF
CofO Issued 10/26/2022 DEROLD HAUFF
Permit Finaled 10/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 8/25/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/26/2021 RENZ SORIANO
Low Impact Development Cleared 12/8/2021 JONATAN VELASQUEZ
Roof/Waste drainage to street Cleared 12/16/2021 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/23/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/10/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/16/2022 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/21/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2022 Approved ANTHONY EGSON
Special/Order Compliance 4/14/2022 Approved HORACE FULTZ
Underground Mechanical 4/14/2022 Approved ANTHONY EGSON
Wood Frame 5/11/2022 Approved ANTHONY EGSON
Pre-Inspection 5/16/2022 Approved ANTHONY EGSON
Wood Frame 5/18/2022 Approved ANTHONY EGSON
HVAC-Rough 5/25/2022 Approved ANTHONY EGSON
PLUMBING-Rough 5/25/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Approved ANTHONY EGSON
ELECTRICAL-Rough 6/1/2022 Approved ANTHONY EGSON
Sewer 6/6/2022 Approved ANTHONY EGSON
BUILDING-Rough-Frame 6/7/2022 Approved ANTHONY EGSON
Green Building Rough 6/7/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/9/2022 Approved ANTHONY EGSON
Shower Pan 6/10/2022 Approved ANTHONY EGSON
Drywall Nailing 6/21/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/21/2022 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 6/28/2022 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 8/23/2022 Approved ANTHONY EGSON
HVAC-Final 8/23/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 8/23/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 9/14/2022 Approved ANTHONY EGSON
Final 9/14/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Final 9/14/2022 Approved ANTHONY EGSON
HVAC-Final 9/14/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Final 9/14/2022 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/14/2022 SGSOV Approved ANTHONY EGSON
Smoke Detectors 9/14/2022 Approved ANTHONY EGSON
ELECTRICAL-Final 10/3/2022 Approved ANTHONY EGSON
Final 10/3/2022 OK to Issue CofO ANTHONY EGSON
HVAC-Final 10/3/2022 Approved ANTHONY EGSON
PLUMBING-Final 10/3/2022 Approved ANTHONY EGSON
Service/Power Release 10/3/2022 Approved ANTHONY EGSON