7397 W 85TH ST 90045

Certificate Information: 7397 W 85TH ST 90045

Application / Permit
21014-10000-02971
Plan Check / Job No.
B21LA11084
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
APPROXIMATELY 220 SQ.FT. ADDITION AT REAR OF EXISTING PROPERTY. ADDING A BATHROOM. RELOCATING EXISTING BATHROOM. UPGRADING KITCHEN. REPLACING WINDOWS. 1 OF 2
Permit Issued
Issued on 9/21/2021
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 RAHEL BEYENE
Corrections Issued 7/2/2021 RAHEL BEYENE
Applicant returned to address corrections 8/3/2021 DANIEL SANJUAN
Applicant returned to address corrections 8/31/2021 RAHEL BEYENE
Plan Check Approved 9/3/2021 RAHEL BEYENE
Issued 9/21/2021 APPLICANT
Building Plans Picked Up 9/24/2021 APPLICANT
CofO in Progress 3/14/2022 BOBBY KEY
CofO in Progress 3/15/2022 BOBBY KEY
CofO Issued 3/22/2022 DANIEL ORRANTE
Permit Finaled 3/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/22/2021 ANTHONY MAINEZ
Sewer availability Cleared 8/2/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 8/4/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 8/19/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,
Engineer Bryson,, Michael Butler; Lic. No.: S4979 5318 E 2ND ST 679      LONG BEACH, CA 90803

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/8/2021 Approved BRENDAN LOONEY
Wood Frame 10/16/2021 Partial Approval JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Corrections Issued BOBBY KEY
Deputy Wood Construction 11/3/2021 Conditional Approval BOBBY KEY
Rough-Elec/Plmb/HVAC 11/17/2021 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 12/8/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 12/8/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/8/2021 Conditional Approval DAVID FEILER
Green Building Rough 12/8/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 12/8/2021 Approved DAVID FEILER
METHANE-Rough 12/8/2021 Approved DAVID FEILER
PLUMBING-Rough 12/8/2021 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 12/13/2021 Partial Approval BOBBY KEY
ELECTRICAL-Rough 12/13/2021 Approved BOBBY KEY
Green Building Rough 12/13/2021 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 12/13/2021 Approved BOBBY KEY
BUILDING-Rough-Frame 12/22/2021 Approved BOBBY KEY
Green Building Rough 12/22/2021 Approved BOBBY KEY
Interior/Exterior Lathing 12/22/2021 Partial Approval BOBBY KEY
Insulation 12/27/2021 Approved BOBBY KEY
Drywall Nailing 12/30/2021 Approved BOBBY KEY
Final 12/30/2021 Corrections Issued BOBBY KEY
ELECTRICAL-Final 3/4/2022 Partial Inspection DAVID FEILER
Final 3/4/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 3/4/2022 Approved DAVID FEILER
Green Building Final 3/4/2022 Approved DAVID FEILER
HVAC-Final 3/4/2022 Partial Inspection DAVID FEILER
METHANE-Barrier 3/4/2022 Approved DAVID FEILER
METHANE-Subgrade 3/4/2022 Approved DAVID FEILER
PLUMBING-Final 3/4/2022 Partial Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 3/4/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 3/4/2022 Approved DAVID FEILER
ELECTRICAL-Final 3/8/2022 Approved BOBBY KEY
Final 3/8/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 3/8/2022 Approved BOBBY KEY
PLUMBING-Final 3/8/2022 Approved BOBBY KEY
Final 3/14/2022 OK to Issue CofO BOBBY KEY