8620 S KENTWOOD AVE 90045
Certificate Information: 8620 S KENTWOOD AVE 90045
- Application / Permit
- 21014-10000-02970
- Plan Check / Job No.
- B21LA11051
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU AT REAR OF LOT.
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | JOE VO |
| Corrections Issued | 7/20/2021 | JOE VO |
| Quality Review Completed | 7/25/2021 | PRANITA SHAH |
| Applicant returned to address corrections | 8/25/2021 | JOE VO |
| Plan Check Approved | 12/3/2021 | JOE VO |
| Issued | 12/8/2021 | APPLICANT |
| CofO in Progress | 5/26/2023 | BOBBY KEY |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
| CofO Issued | 6/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 8/3/2021 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 9/19/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 9/20/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 10/5/2021 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 11/22/2021 | FREDDY GARCIA |
| Address approval | Cleared | 11/23/2021 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 11/23/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 11/23/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/26/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 4/26/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/6/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 7/19/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/19/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/20/2022 | Approved | RICHARD STEINBACH |
| Gas Test | 7/20/2022 | Partial Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 7/27/2022 | Approved | BOBBY KEY |
| Final | 7/27/2022 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2022 | Approved | BOBBY KEY |
| Green Building Rough | 7/27/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 7/27/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 7/27/2022 | Approved | BOBBY KEY |
| Sewer | 7/27/2022 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 8/1/2022 | Partial Inspection | BOBBY KEY |
| Sewer | 8/1/2022 | Approved | BOBBY KEY |
| Insulation | 8/4/2022 | Corrections Issued | CLAYTON GRAHAM |
| Underground Mechanical | 8/4/2022 | Approved | CLAYTON GRAHAM |
| Gas Test | 8/5/2022 | Partial Approval | BOBBY KEY |
| Insulation | 8/8/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 8/18/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 8/23/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 3/16/2023 | Approved | BOBBY KEY |
| Final | 3/16/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 3/16/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/16/2023 | Corrections Issued | BOBBY KEY |
| Smoke Detectors | 3/16/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 3/16/2023 | Partial Inspection | JESUS PINEDA |
| Final | 3/20/2023 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 3/20/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 3/20/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 3/20/2023 | SGSOV Approved | BOBBY KEY |
| Final | 5/26/2023 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 5/26/2023 | Approved | BOBBY KEY |