5237-5237 1-2 N LEGHORN AVE 91401

Certificate Information: 5237-5237 1-2 N LEGHORN AVE 91401

Application / Permit
21014-10000-02961
Plan Check / Job No.
B21LA11011
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GROUND FLOOR ADDITION TO EXISTING GARAGE AND CONVERT TO ADU. FULLY SPRINKLERED
Permit Issued
Issued on 10/21/2021
Issuing Office
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 JOE VO
Corrections Issued 7/25/2021 JOE VO
Quality Review Completed 8/2/2021 MICHAEL PEREZ
Applicant returned to address corrections 8/13/2021 JOE VO
Applicant returned to address corrections 8/25/2021 JOE VO
Applicant returned to address corrections 9/8/2021 JOE VO
Plan Check Approved 10/18/2021 JOE VO
Issued 10/21/2021 APPLICANT
CofO in Progress 11/20/2023 KIRK SANDERS
Permit Finaled 1/18/2024 RUBEN SALAS
CofO Issued 1/18/2024 RUBEN SALAS
Permit Finaled 1/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/17/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/17/2021 CARLOS AGUILERA
Sewer availability Cleared 8/18/2021 CARLOS AGUILERA
Private street Cleared 8/23/2021 ANNA VIDAL
Low Impact Development Cleared 10/4/2021 LONDY ALVARADO
Roof/Waste drainage to street Cleared 10/4/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/7/2021 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/27/2022 Corrections Issued CHRISTOPHE COCHRAN
Underground Mechanical 4/29/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/9/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/18/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 8/12/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Rough 8/12/2022 Approved RAFAEL CORTES
Green Building Rough 8/12/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 8/12/2022 Partial Approval RAFAEL CORTES
Gas Test 8/31/2022 Corrections Issued RAFAEL CORTES
Sewer 8/31/2022 Partial Approval RAFAEL CORTES
PLUMBING-Rough 9/9/2022 Partial Approval RAFAEL CORTES
Underground Mechanical 9/9/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 10/5/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 10/5/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Rough 10/5/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Rough 10/5/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready RAFAEL CORTES
Underground Mechanical 10/5/2022 Approved RAFAEL CORTES
Wood Frame 10/5/2022 Not Ready for Inspection RAFAEL CORTES
BUILDING-Rough-Frame 10/28/2022 Corrections Issued CALEB MEISTER
Green Building Rough 10/28/2022 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 11/4/2022 Approved WILLIAM WREN
Green Building Rough 11/4/2022 Approved WILLIAM WREN
HVAC-Rough 11/4/2022 No Access for Inspection WILLIAM WREN
Interior/Exterior Lathing 11/4/2022 Approved WILLIAM WREN
HVAC-Rough 11/22/2022 Approved JOHN COLEMAN
PLUMBING-Rough 12/5/2022 Approved KIRK SANDERS
Insulation 12/14/2022 Corrections Issued KIRK SANDERS
Insulation 12/23/2022 Not Ready for Inspection KIRK SANDERS
Insulation 1/12/2023 Approved KIRK SANDERS
Drywall Nailing 1/20/2023 Approved KIRK SANDERS
ELECTRICAL-Final 4/18/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 4/19/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 9/27/2023 Corrections Issued KIRK SANDERS
Final 9/27/2023 Corrections Issued KIRK SANDERS
Green Building Final 9/27/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Final 9/27/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 9/27/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 9/27/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 9/29/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 11/15/2023 Corrections Issued KIRK SANDERS
Final 11/15/2023 Not Ready for Inspection KIRK SANDERS
Green Building Final 11/15/2023 Approved KIRK SANDERS
HVAC-Final 11/15/2023 Approved KIRK SANDERS
PLUMBING-Final 11/15/2023 Partial Approval KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 11/15/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 11/15/2023 Approved KIRK SANDERS
Final 11/17/2023 OK to Issue CofO KIRK SANDERS