9531 N ORION AVE 91343

Certificate Information: 9531 N ORION AVE 91343

Application / Permit
21014-10000-02932
Plan Check / Job No.
B21LA10967
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
STRUCTURAL REMODEL AND GROUND FLOOR ADDITION TO 1-STORY SFD. STRUCTURAL REMODEL TO EXISTING 2 CAR GARAGE, PER PLAND.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 5/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 MAHNAZ NOURHASHEMI
Corrections Issued 7/22/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 7/29/2021 JASON HEALEY
Plan Check Approved 1/14/2022 MAHNAZ NOURHASHEMI
Issued 2/14/2022 APPLICANT
Building Plans Picked Up 2/15/2022 APPLICANT
CofO in Progress 5/22/2024 VINCENT HANLEY
Permit Finaled 5/31/2024 RUBEN SALAS
CofO Issued 5/31/2024 RUBEN SALAS
Permit Finaled 5/31/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/27/2021 LEE GUILBEAUX
Low Impact Development Cleared 12/6/2021 TA ANH
Roof/Waste drainage to street Cleared 12/9/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/3/2022 Conditional Approval MICHAEL SMITH
Excavation/Setback/Form/Re-Bar 11/15/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 11/15/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/30/2022 Partial Approval GREGG CUMMINGS
Insulation 11/30/2022 Partial Approval GREGG CUMMINGS
PLUMBING-Rough 11/30/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/2/2022 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 1/17/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/3/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 2/3/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 2/10/2023 Approved CHRISTOPHER DELLEFIELD
MERV13>=Rough 2/10/2023 Approved CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 2/10/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/15/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Approved CHRISTOPHER DELLEFIELD
Rough-Elec/Plmb/HVAC 2/15/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/24/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 2/28/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/3/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 3/3/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/7/2023 Approved CHRISTOPHER DELLEFIELD
Final 5/6/2024 Corrections Issued DAVID ANDERSON
Green Building Final 5/6/2024 Approved DAVID ANDERSON
MERV13>=Final 5/6/2024 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/6/2024 SGSOV Approved DAVID ANDERSON
Smoke Detectors 5/6/2024 Not Ready for Inspection DAVID ANDERSON
Final 5/9/2024 Corrections Issued KIRK SANDERS
Smoke Detectors 5/9/2024 Approved KIRK SANDERS
ELECTRICAL-Final 5/21/2024 Approved VINCENT HANLEY
Final 5/21/2024 OK to Issue CofO VINCENT HANLEY
HVAC-Final 5/21/2024 Approved VINCENT HANLEY
PLUMBING-Final 5/21/2024 Approved VINCENT HANLEY