1341 S CLUB VIEW DR 90024

Certificate Information: 1341 S CLUB VIEW DR 90024

Application / Permit
21014-10000-02926
Plan Check / Job No.
B21LA10927
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE NEW ADDITION AND REMODEL SINGLE FAMILY RESIDENCE. THREE STORY WITH ATTACHED GARAGE. NEW ELEVATOR. (NFPA 13D THRU OUT)
Permit Issued
Issued on 5/24/2022
Issuing Office
Metro
Current Status
Issued on 5/24/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 AUNG SOE
Corrections Issued 8/17/2021 AUNG SOE
Quality Review Completed 8/19/2021 EUGENE BARBEAU
Building Plans Picked Up 8/25/2021 APPLICANT
Applicant returned to address corrections 10/28/2021 AUNG SOE
Applicant returned to address corrections 3/29/2022 AUNG SOE
Applicant returned to address corrections 5/6/2022 AUNG SOE
Plan Check Approved 5/18/2022 AUNG SOE
Issued 5/24/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/16/2021 AUNG SOE
Specific Plan Cleared 3/14/2022 FREDDY GARCIA
Hydrant and Access approval Cleared 4/26/2022 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 5/5/2022 TRACY TATE
Low Impact Development Cleared 5/5/2022 ANDRES COVARRUBIAS
Sewer availability Cleared 5/5/2022 TRACY TATE
Roof/Waste drainage to street Cleared 5/13/2022 TRACY TATE

Contact Information

Architect Mcvay,, Bruce Cameron; Lic. No.: C11870 6440 E. EL ROBLE STREET      LONG BEACH, CA 90815
Contractor Inland Framing & Development; Lic. No.: 505887-B 1452 NORTH EASTERN AVENUE      LOS ANGELES, CA 90063
Engineer Perez,, Celso; Lic. No.: C81768 7941 YOLANDA AVE      RESEDA, CA 91335

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/29/2022 Conditional Approval BRENDAN LOONEY
Deputy Drilled-In Anchors 7/12/2022 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 7/13/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/13/2022 Partial Approval JUAN VALENZUELA
METHANE-Barrier 7/13/2022 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 7/13/2022 Corrections Issued JUAN VALENZUELA
Deputy Reinf. Concrete 7/14/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 7/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 7/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
METHANE-Rough 7/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 7/28/2022 Partial Approval CHRISTOPHER WILSON
METHANE-Barrier 8/2/2022 Not Ready for Inspection PATRICK QUALEY
METHANE-Subgrade 8/2/2022 Partial Inspection PATRICK QUALEY
Pre-Inspection 8/2/2022 Partial Inspection PATRICK QUALEY
Wood Frame 8/2/2022 Not Ready for Inspection PATRICK QUALEY
Wood Frame 8/4/2022 Partial Approval PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval ANDREW NAVE
Deputy Methane Barrier 8/18/2022 Approved ANDREW NAVE
METHANE-Subgrade 8/18/2022 Approved ANDREW NAVE
Deputy Methane Barrier 8/22/2022 Approved MICHAEL PELHAM
METHANE-Barrier 8/24/2022 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 9/13/2022 Approved STEPHANIE SWANSON
Footing/Foundation/Slab 9/13/2022 Approved STEPHANIE SWANSON
Deputy Reinf. Concrete 9/22/2022 Conditional Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 10/19/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 12/20/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Partial Approval STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/29/2022 Corrections Issued ASHLEY THOMPSON
Deputy Methane Barrier 1/20/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 1/27/2023 Approved STEPHANIE SWANSON
Reinforced Masonry Frame 5/8/2023 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 5/23/2023 Partial Approval BRENDAN LOONEY
Special/Order Compliance 5/23/2023 Partial Inspection MICHAEL PELHAM
Deputy Reinf. Masonry 6/22/2023 Conditional Approval MICHAEL PELHAM
Deputy Reinf. Masonry 6/23/2023 Conditional Approval MICHAEL PELHAM
Masonry Wall/Backfill 7/21/2023 Corrections Issued STEPHANIE SWANSON
Masonry Wall/Backfill 9/27/2023 Corrections Issued STEPHANIE SWANSON
Masonry Wall/Backfill 9/29/2023 Partial Approval STEPHANIE SWANSON
HVAC-Rough 5/21/2024 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 5/21/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 5/31/2024 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 5/31/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/12/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 6/12/2024 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 6/12/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 7/23/2024 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 8/2/2024 Conditional Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/8/2024 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/8/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 9/5/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Not Ready for Inspection STEPHANIE SWANSON
HVAC-Rough 9/5/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 10/4/2024 Partial Approval STEPHANIE SWANSON
Deputy Shotcrete 11/6/2024 Conditional Approval MICHAEL PELHAM
Interior/Exterior Lathing 11/19/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 12/12/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 12/12/2024 Approved STEPHANIE SWANSON
METHANE-Rough 12/12/2024 Approved STEPHANIE SWANSON
Verify Sprinkler Sign Off 12/12/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 12/16/2024 Partial Approval STEPHANIE SWANSON
Insulation 12/31/2024 Not Ready for Inspection STEPHANIE SWANSON
Insulation 1/7/2025 Corrections Issued STEPHANIE SWANSON
Insulation 1/27/2025 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 2/19/2025 Partial Approval STEPHANIE SWANSON
Drywall Nailing 3/3/2025 Partial Approval STEPHANIE SWANSON
Drywall Nailing 4/2/2025 Partial Approval DANIEL VERA
BUILDING-Rough-Frame 4/15/2025 Corrections Issued DANIEL VERA
BUILDING-Rough-Frame 4/30/2025 Partial Approval DANIEL VERA
Interior/Exterior Lathing 5/7/2025 Approved DANIEL VERA
ELECTRICAL-Final 8/21/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 11/4/2025 Partial Approval DANIEL VERA
ELECTRICAL-Rough 11/4/2025 Approved DANIEL VERA
ELECTRICAL-Final 1/22/2026 Corrections Issued WILBER ROSALES
Special/Order Compliance 1/22/2026 Partial Inspection DAKOTA LOW
ELECTRICAL-Final 1/28/2026 Approved RYAN SALAZAR
Service/Power Release 4/9/2026 Approved CHRISTOPHER WILSON
Special/Order Compliance 5/20/2026 Corrections Issued ANDREW NAVE