1341 S CLUB VIEW DR 90024
Certificate Information: 1341 S CLUB VIEW DR 90024
- Application / Permit
- 21014-10000-02926
- Plan Check / Job No.
- B21LA10927
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE NEW ADDITION AND REMODEL SINGLE FAMILY RESIDENCE. THREE STORY WITH ATTACHED GARAGE. NEW ELEVATOR. (NFPA 13D THRU OUT)
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Metro
- Current Status
- Issued on 5/24/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | AUNG SOE |
| Corrections Issued | 8/17/2021 | AUNG SOE |
| Quality Review Completed | 8/19/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 8/25/2021 | APPLICANT |
| Applicant returned to address corrections | 10/28/2021 | AUNG SOE |
| Applicant returned to address corrections | 3/29/2022 | AUNG SOE |
| Applicant returned to address corrections | 5/6/2022 | AUNG SOE |
| Plan Check Approved | 5/18/2022 | AUNG SOE |
| Issued | 5/24/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/16/2021 | AUNG SOE |
| Specific Plan | Cleared | 3/14/2022 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 4/26/2022 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2022 | TRACY TATE |
| Low Impact Development | Cleared | 5/5/2022 | ANDRES COVARRUBIAS |
| Sewer availability | Cleared | 5/5/2022 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 5/13/2022 | TRACY TATE |
Contact Information
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Inland Framing & Development; Lic. No.: 505887-B | 1452 NORTH EASTERN AVENUE LOS ANGELES, CA 90063 |
| Engineer | Perez,, Celso; Lic. No.: C81768 | 7941 YOLANDA AVE RESEDA, CA 91335 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/29/2022 | Conditional Approval | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 7/12/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/13/2022 | Partial Approval | JUAN VALENZUELA |
| METHANE-Barrier | 7/13/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Subgrade | 7/13/2022 | Corrections Issued | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 7/14/2022 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 7/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| METHANE-Rough | 7/28/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | CHRISTOPHER WILSON |
| METHANE-Barrier | 8/2/2022 | Not Ready for Inspection | PATRICK QUALEY |
| METHANE-Subgrade | 8/2/2022 | Partial Inspection | PATRICK QUALEY |
| Pre-Inspection | 8/2/2022 | Partial Inspection | PATRICK QUALEY |
| Wood Frame | 8/2/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Wood Frame | 8/4/2022 | Partial Approval | PATRICK QUALEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Partial Approval | ANDREW NAVE |
| Deputy Methane Barrier | 8/18/2022 | Approved | ANDREW NAVE |
| METHANE-Subgrade | 8/18/2022 | Approved | ANDREW NAVE |
| Deputy Methane Barrier | 8/22/2022 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 8/24/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/13/2022 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 9/22/2022 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/19/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/29/2022 | Corrections Issued | ASHLEY THOMPSON |
| Deputy Methane Barrier | 1/20/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Approved | STEPHANIE SWANSON |
| Reinforced Masonry Frame | 5/8/2023 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 5/23/2023 | Partial Approval | BRENDAN LOONEY |
| Special/Order Compliance | 5/23/2023 | Partial Inspection | MICHAEL PELHAM |
| Deputy Reinf. Masonry | 6/22/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Masonry | 6/23/2023 | Conditional Approval | MICHAEL PELHAM |
| Masonry Wall/Backfill | 7/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Masonry Wall/Backfill | 9/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Masonry Wall/Backfill | 9/29/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 5/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/21/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/31/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 5/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/12/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/12/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/23/2024 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Wood Construction | 8/2/2024 | Conditional Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 8/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 8/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 9/5/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 9/5/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 10/4/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Shotcrete | 11/6/2024 | Conditional Approval | MICHAEL PELHAM |
| Interior/Exterior Lathing | 11/19/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 12/12/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 12/12/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 12/12/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/16/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 12/31/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 1/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 1/27/2025 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 2/19/2025 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 3/3/2025 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 4/2/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 4/15/2025 | Corrections Issued | DANIEL VERA |
| BUILDING-Rough-Frame | 4/30/2025 | Partial Approval | DANIEL VERA |
| Interior/Exterior Lathing | 5/7/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 8/21/2025 | Not Ready for Inspection | DANIEL VERA |
| BUILDING-Rough-Frame | 11/4/2025 | Partial Approval | DANIEL VERA |
| ELECTRICAL-Rough | 11/4/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 1/22/2026 | Corrections Issued | WILBER ROSALES |
| Special/Order Compliance | 1/22/2026 | Partial Inspection | DAKOTA LOW |
| ELECTRICAL-Final | 1/28/2026 | Approved | RYAN SALAZAR |
| Service/Power Release | 4/9/2026 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 5/20/2026 | Corrections Issued | ANDREW NAVE |