1350 N ARMADALE AVE 90042
Certificate Information: 1350 N ARMADALE AVE 90042
- Application / Permit
- 21014-10000-02917
- Plan Check / Job No.
- B21LA10891
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF EXISTING CRAWL SPACE AND GROUND FLOOR ADDITION TO (E) SFD.
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 9/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2021 | KHEDER ALRAZAA |
| Corrections Issued | 8/3/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 8/5/2021 | JASON HEALEY |
| Applicant returned to address corrections | 11/9/2021 | KHEDER ALRAZAA |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Plan Check Approved | 12/7/2021 | KHEDER ALRAZAA |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 9/11/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
| CofO Issued | 9/13/2025 | DEROLD HAUFF |
| Permit Finaled | 9/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/2/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 10/2/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 10/2/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 10/2/2021 | RENZ SORIANO |
| BHO/Hillside ordinance | Cleared | 10/2/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 10/22/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/22/2021 | RENZ SORIANO |
| Grading Pre-Inspection | Cleared | 12/7/2021 | KHEDER ALRAZAA |
Contact Information
| Contractor | Beckley Juan Miguel; Lic. No.: 1014693-B | 5830 RESEDA BLVD #140 TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 5/27/2022 | Partial Approval | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 6/27/2022 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/22/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 8/24/2022 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 8/29/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/15/2022 | Approved | AMY COLIN |
| Reinforced Masonry Frame | 9/26/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Masonry Wall/Backfill | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/28/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 4/19/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 4/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 4/24/2023 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/24/2023 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 4/24/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Deputy Wood Construction | 5/2/2023 | Conditional Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/8/2023 | Partial Approval | CRAIG VAUGHAN |
| Shower Pan | 5/8/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/8/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 5/11/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/11/2023 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 5/11/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/11/2023 | Corrections Issued | CRAIG VAUGHAN |
| Wood Frame | 5/11/2023 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/20/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 6/20/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 6/20/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/29/2023 | Corrections Issued | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 6/29/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/17/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 7/17/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/17/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 8/14/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 6/7/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/7/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 6/7/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/7/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/7/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/7/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/8/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/8/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 3/25/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Not Ready | DAVID WILLIAMS |
| Final | 4/1/2025 | OK to Issue CofO | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 4/1/2025 | SGSOV Approved | DAVID WILLIAMS |