8315 S COLEGIO DR 90045

Certificate Information: 8315 S COLEGIO DR 90045

Application / Permit
21014-10000-02904
Plan Check / Job No.
B21LA10860
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION FOR NEW MASTER BEDROOM W/CLOSET AND BATHROOM. RELOCATED (E) BATHROOM
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
CofO Issued on 9/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 RICARDO RAMIREZ
Plans on Hold 11/26/2021 RICARDO RAMIREZ
Hold Released 1/4/2022 FERNANDO FLORES
Plan Check Approved 1/7/2022 FERNANDO FLORES
Issued 1/10/2022 APPLICANT
Building Plans Picked Up 1/11/2022 APPLICANT
CofO in Progress 8/31/2022 BOBBY KEY
CofO Issued 9/10/2022 DANIEL ORRANTE
Permit Finaled 9/10/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 7/22/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/26/2021 DINAH GARIN
Low Impact Development Cleared 9/15/2021 SAHIL SHARMA
Grading Pre-Inspection Cleared 11/29/2021 RICARDO RAMIREZ
Roof/Waste drainage to street Cleared 12/28/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/31/2022 Partial Approval BOBBY KEY
Excavation/Setback/Form/Re-Bar 2/9/2022 Approved BOBBY KEY
Footing/Foundation/Slab 2/9/2022 Approved BOBBY KEY
ELECTRICAL-Rough 4/6/2022 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Approved BOBBY KEY
HVAC-Rough 4/6/2022 Approved BOBBY KEY
PLUMBING-Rough 4/6/2022 Partial Approval BOBBY KEY
Sewer 4/14/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 4/21/2022 Approved BOBBY KEY
Green Building Rough 4/21/2022 Approved BOBBY KEY
Interior/Exterior Lathing 4/21/2022 Partial Approval BOBBY KEY
PLUMBING-Rough 4/21/2022 Approved BOBBY KEY
ELECTRICAL-Final 4/27/2022 Corrections Issued BOBBY KEY
Insulation 4/27/2022 Approved BOBBY KEY
Drywall Nailing 5/4/2022 Approved DAVID FEILER
Final 7/13/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 7/13/2022 Corrections Issued JESUS RODRIGUEZ
METHANE-Final 7/13/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/13/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 7/13/2022 Corrections Issued JESUS RODRIGUEZ
Final 7/19/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 7/19/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/19/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 7/19/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 7/22/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/22/2022 Approved HERBERT GIRON
ELECTRICAL-Final 7/26/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 7/26/2022 Approved BOBBY KEY
ELECTRICAL-Final 8/31/2022 Approved BOBBY KEY
Final 8/31/2022 OK to Issue CofO BOBBY KEY