6453 W 80TH PL 90045

Certificate Information: 6453 W 80TH PL 90045

Application / Permit
21014-10000-02865
Plan Check / Job No.
B21LA10752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SFD. NEW PORCH ADDITION AT THE FRONT OF (E) SFD.
Permit Issued
Issued on 10/19/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/14/2021 FARSHAD ALIMOHAMADI
Corrections Issued 6/15/2021 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/14/2022 FARSHAD ALIMOHAMADI
Plan Check Approved 3/31/2022 RICARDO RAMIREZ
Plan Check Approved 8/17/2022 KHUONG TRUONG
Building Plans Picked Up 8/19/2022 APPLICANT
Issued 10/19/2022 APPLICANT
CofO in Progress 7/19/2023 HERBERT GIRON
Permit Finaled 7/24/2023 DANIEL ORRANTE
CofO Issued 7/24/2023 DANIEL ORRANTE
Permit Finaled 7/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/23/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 6/28/2021 THOMAS LANG
Specific Plan Cleared 1/25/2022 EDUARDO HERMOSO
Low Impact Development Cleared 1/26/2022 TA ANH

Contact Information

Contractor A T A Construction Inc; Lic. No.: 1044074-B 9109 GREGORY WAY      BEVERLY HILLS, CA 90211
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/18/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/18/2022 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 11/22/2022 Approved HERBERT GIRON
Green Building Rough 11/22/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/5/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 12/5/2022 Partial Approval HERBERT GIRON
Wood Frame 12/5/2022 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 12/7/2022 Partial Approval HERBERT GIRON
Deputy Steel/Welding 12/7/2022 Approved HERBERT GIRON
Insulation 12/7/2022 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Partial Approval HERBERT GIRON
Deputy Reinf. Concrete 12/13/2022 Conditional Approval HERBERT GIRON
Deputy Wood Construction 12/13/2022 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 2/10/2023 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 2/10/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 2/10/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/10/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 2/28/2023 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 3/8/2023 Conditional Approval HERBERT GIRON
Footing/Foundation/Slab 3/8/2023 Approved HERBERT GIRON
ELECTRICAL-Rough 3/13/2023 Corrections Issued HERBERT GIRON
HVAC-Rough 3/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 3/16/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Approved HERBERT GIRON
HVAC-Rough 3/16/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved HERBERT GIRON
HVAC-Rough 3/20/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/30/2023 Approved HERBERT GIRON
Green Building Rough 3/30/2023 Approved HERBERT GIRON
HVAC-Rough 3/30/2023 Approved HERBERT GIRON
Interior/Exterior Lathing 3/30/2023 Approved HERBERT GIRON
Shower Pan 3/30/2023 Approved HERBERT GIRON
Insulation 4/4/2023 Approved HERBERT GIRON
Drywall Nailing 4/19/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 7/6/2023 Corrections Issued HERBERT GIRON
Gas Test 7/6/2023 Approved HERBERT GIRON
HVAC-Final 7/6/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 7/6/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 7/6/2023 Approved HERBERT GIRON
ELECTRICAL-Final 7/12/2023 Approved HERBERT GIRON
Final 7/12/2023 Corrections Issued HERBERT GIRON
Green Building Final 7/12/2023 Approved HERBERT GIRON
HVAC-Final 7/12/2023 Approved HERBERT GIRON
PLUMBING-Final 7/12/2023 Approved HERBERT GIRON
Special/Order Compliance 7/12/2023 Partial Inspection BOBBY KEY
Final 7/19/2023 OK to Issue CofO HERBERT GIRON