8828 S CIMARRON ST 90047

Certificate Information: 8828 S CIMARRON ST 90047

Application / Permit
21014-10000-02851
Plan Check / Job No.
B21LA10674
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) 1-STORY GARAGE AND CONVERT THE ENTIRE BUILDING TO 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
CofO Issued on 8/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 DANIEL YIP
Corrections Issued 6/28/2021 DANIEL YIP
Quality Review Completed 7/7/2021 JASON HEALEY
Plan Check Approved 10/8/2021 DANIEL YIP
Building Plans Picked Up 11/22/2021 APPLICANT
Issued 6/20/2023 APPLICANT
CofO in Progress 8/4/2025 WAYNE REGESTER
Permit Finaled 8/9/2025 DEROLD HAUFF
CofO Issued 8/9/2025 DEROLD HAUFF
Permit Finaled 8/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/20/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 7/21/2021 THOMAS LANG
Sewer availability Cleared 7/21/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 7/22/2021 THOMAS LANG
Hydrant and Access approval Cleared 9/10/2021 MATTHEW CRAIG

Contact Information

Architect Diaz,, Enrique; Lic. No.: C33905 8309 EDMARU AVENUE      WHITTIER, CA 90605
Contractor Zepeda'S Construction; Lic. No.: 868625-B 14790 SAN FELICIANO DRIVE      LA MIRADA, CA 90638
Engineer Liu,, Frank; Lic. No.: C64806 PO BOX 212      ARTESIA, CA 90702

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/30/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 7/5/2023 Corrections Issued ENRIQUE MIRELES
METHANE-Barrier 7/5/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 7/5/2023 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Rough 7/12/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 8/7/2023 Approved ENRIQUE MIRELES
HVAC-Rough 8/7/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 8/7/2023 Approved ENRIQUE MIRELES
Insulation 8/11/2023 Approved ENRIQUE MIRELES
Drywall Nailing 8/16/2023 Approved ENRIQUE MIRELES
Green Building Rough 8/16/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 10/2/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/2/2023 Approved ENRIQUE MIRELES
Final 10/2/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 10/2/2023 Approved ENRIQUE MIRELES
Green Building Final 10/2/2023 Approved ENRIQUE MIRELES
HVAC-Final 10/2/2023 Approved ENRIQUE MIRELES
METHANE-Barrier 10/2/2023 Approved ENRIQUE MIRELES
METHANE-Subgrade 10/2/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 10/2/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/2/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/2/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Final 10/5/2023 Approved ENRIQUE MIRELES
Final 10/5/2023 Corrections Issued ENRIQUE MIRELES
HVAC-Final 10/5/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 10/5/2023 Approved ENRIQUE MIRELES
Final 12/4/2024 No Access for Inspection AMIR NAZARIAN
Final 12/19/2024 Not Ready for Inspection JOHN QUINTANILLA
Final 8/1/2025 OK to Issue CofO WAYNE REGESTER