720 N MILO TER 90042
Certificate Information: 720 N MILO TER 90042
- Application / Permit
- 21014-10000-02844
- Plan Check / Job No.
- B21LA10639
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO AN EXISTING 1-STORY SINGLE FAMILY DWELLING WITH ADDITION (6'-0" X 11'-10") AND (E) PATIO ENCLOSURE (5'-8 1/2" X 6'-0").
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- CofO Issued on 2/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/11/2021 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/12/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 8/5/2021 | JESSE ARELLANO |
| Issued | 8/23/2021 | APPLICANT |
| Building Plans Picked Up | 8/24/2021 | APPLICANT |
| CofO in Progress | 2/14/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
| Permit Finaled | 2/26/2023 | DEROLD HAUFF |
| CofO Issued | 2/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/24/2021 | BRIAN MILLER |
| Roof/Waste drainage to street | Cleared | 6/28/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | RENZ SORIANO |
Contact Information
| Contractor | A G A Construction Inc; Lic. No.: 918705-B | 18375 VENTURA BLVD # 548 TARZANA, CA 91356 |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/13/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 11/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/8/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deputy Drilled-In Anchors | 11/10/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2021 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2021 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 2/9/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/9/2022 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 2/9/2022 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 2/25/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 2/25/2022 | Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/25/2022 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Insulation | 3/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 3/4/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Shower Pan | 3/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 3/8/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/8/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 3/8/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| HVAC-Rough | 3/11/2022 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/11/2022 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 4/1/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 8/4/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/4/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 1/4/2023 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 2/13/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |