3318 1/2 W GLENHURST AVE 90039
Certificate Information: 3318 1/2 W GLENHURST AVE 90039
- Application / Permit
- 21014-10000-02843
- Plan Check / Job No.
- B21LA10634
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** PROPOSED ADDITION TO THE REAR OF EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 12/28/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/11/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/14/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 12/13/2023 | SELLA BENYAMIN |
| Plan Check Approved | 12/23/2023 | SELLA BENYAMIN |
| Issued | 12/28/2023 | APPLICANT |
| CofO in Progress | 2/25/2025 | THOMAS LOGRASSO |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
| CofO Issued | 3/2/2025 | DEROLD HAUFF |
| Permit Finaled | 3/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2021 | CELINA MORENO |
| ZI | Cleared | 7/26/2021 | TERRI OSBORNE |
| Low Impact Development | Cleared | 10/9/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 10/12/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | CELINA MORENO |
| Sewer availability | Cleared | 10/16/2023 | CELINA MORENO |
| Construction within easement | Cleared | 12/4/2023 | RIDWAN HARDY |
Contact Information
| Architect | Gensler,, Aaron H; Lic. No.: NA38246 | , |
| Contractor | Owner-Builder | , |
| Engineer | Gorbin,, James D; Lic. No.: S5859 | 210 S JUANITA AVE UNIT A REDONDO BEACH, CA 90277 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2024 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 7/10/2024 | Approved | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 7/11/2024 | Conditional Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 7/16/2024 | Approved | ENRIQUE MIRELES |
| Deputy Wood Construction | 8/7/2024 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 8/23/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 8/23/2024 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 8/23/2024 | Approved | THOMAS LOGRASSO |
| Underground Mechanical | 8/23/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/10/2024 | Corrections Issued | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/10/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 10/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/17/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Shower Pan | 10/17/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 10/22/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 10/22/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 10/22/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Final | 2/7/2025 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 2/7/2025 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 2/7/2025 | Corrections Issued | THOMAS LOGRASSO |
| Final | 2/24/2025 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Not Required | THOMAS LOGRASSO |
| Service/Power Release | 2/24/2025 | Not Required | THOMAS LOGRASSO |
| Smoke Detectors | 2/24/2025 | Approved | THOMAS LOGRASSO |