857-863 N LUCILE AVE 90026

Certificate Information: 857-863 N LUCILE AVE 90026

Application / Permit
21014-10000-02838
Plan Check / Job No.
B21LA10624
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AT 1ST FLOOR WITH STAIRWAY TO (E) TWO STORY SFD BUILDING.
Permit Issued
Issued on 10/12/2022
Issuing Office
Valley
Current Status
Issued on 10/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 6/11/2021 TSE MING HUANG
Corrections Issued 6/12/2021 TSE MING HUANG
Applicant returned to address corrections 1/6/2022 LUKE GONZALES
Plan Check Approved 3/1/2022 ZAW HAN
Building Plans Picked Up 3/2/2022 APPLICANT
Issued 10/12/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/4/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 10/4/2021 RENZ SORIANO
Sewer availability Cleared 11/12/2021 CELINA MORENO
Grading Pre-Inspection Cleared 3/1/2022 ROBERT HUGHES

Contact Information

Contractor Samuels Construction; Lic. No.: 486439-B 6518 BALCOM AVE      RESEDA, CA 91335
Engineer Ng,, Edward Tw; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2022 Approved FREDDIE RIVERA
Deputy Drilled-In Anchors 1/13/2023 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 4/6/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 4/6/2023 Approved FREDDIE RIVERA
Green Building Rough 4/6/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/1/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 9/1/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 9/1/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/11/2023 Approved FREDDIE RIVERA
Green Building Rough 9/11/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/11/2023 Partial Approval FREDDIE RIVERA
PLUMBING-Rough 9/11/2023 Approved FREDDIE RIVERA
Insulation 9/22/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/22/2023 Approved FREDDIE RIVERA
Drywall Nailing 9/29/2023 Approved JEFFREY MEAD
Final 2/13/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 2/13/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 2/13/2024 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 2/13/2024 Partial Inspection FREDDIE RIVERA
Final 2/16/2024 Partial Inspection FREDDIE RIVERA
Final 3/20/2024 Conditional Approval FREDDIE RIVERA
Smoke Detectors 3/20/2024 Approved FREDDIE RIVERA