149 1/2 W 87TH PL 90003
Certificate Information: 149 1/2 W 87TH PL 90003
- Application / Permit
- 21014-10000-02827
- Plan Check / Job No.
- B21LA10542
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ADU AND ADDITION (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | AUNG SOE |
| Corrections Issued | 6/14/2021 | AUNG SOE |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Applicant returned to address corrections | 5/17/2022 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 6/7/2022 | KHUONG TRUONG |
| Issued | 6/30/2022 | APPLICANT |
| CofO in Progress | 11/3/2022 | LILIANA PORTILLO |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
| CofO Issued | 11/5/2022 | DEROLD HAUFF |
| Permit Finaled | 11/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2021 | WALLIE JONG |
| Sewer availability | Cleared | 7/26/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 12/29/2021 | GILBERT URREA |
| Low Impact Development | Cleared | 4/4/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 5/19/2022 | WALLIE JONG |
Contact Information
| Contractor | Nelson General Building Contractor; Lic. No.: 649194-B | 4227 S WESTERN AVE LOS ANGELES, CA 90062 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/18/2022 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/20/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Pre-Inspection | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Rec and Parks Fee Memo | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Wood Frame | 8/4/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/22/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/22/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/22/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/26/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 8/26/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/26/2022 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/30/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/30/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 8/30/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 8/30/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/30/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/31/2022 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 9/6/2022 | Approved | LILIANA PORTILLO |
| Sewer | 9/6/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 9/6/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/14/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/14/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/16/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 10/25/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 11/2/2022 | Approved | LILIANA PORTILLO |
| Final | 11/2/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 11/2/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 11/2/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 11/2/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 11/2/2022 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 11/2/2022 | Approved | LILIANA PORTILLO |