1507 W TORRANCE BLVD 90501

Certificate Information: 1507 W TORRANCE BLVD 90501

Application / Permit
21014-10000-02797
Plan Check / Job No.
B21LA10470
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION AND STRUCTURAL INTERIOR REMODEL TO EXISTING 1-STORY SFD
Permit Issued
Issued on 5/12/2022
Issuing Office
Current Status
Issued on 5/12/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 7/22/2021 MAHNAZ NOURHASHEMI
Corrections Issued 7/27/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 8/5/2021 JASON HEALEY
Building Plans Picked Up 8/13/2021 APPLICANT
Applicant returned to address corrections 9/28/2021 MAHNAZ NOURHASHEMI
Plan Check Approved 5/12/2022 MAHNAZ NOURHASHEMI
Issued 5/12/2022 APPLICANT

Permit Application Clearance Information

Hold Cleared 9/8/2021 JASON SHEETS
Low Impact Development Cleared 2/28/2022 ANTHONY VARGAS
Address approval Cleared 3/2/2022 ERIK BEASLEY
Roof/Waste drainage to street Cleared 3/2/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/21/2022 ERIK BEASLEY
Sewer availability Cleared 3/21/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/6/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 10/6/2022 Approved RYAN SALAZAR
Wood Frame 2/7/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 7/31/2023 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 8/17/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/6/2023 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Corrections Issued EUGENE CASSIDY
Shower Pan 4/4/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/1/2024 Partial Approval EUGENE CASSIDY
Gas Test 5/1/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/21/2024 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 5/21/2024 Partial Approval EUGENE CASSIDY
Insulation 6/7/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/11/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Approved EUGENE CASSIDY
Green Building Rough 6/11/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/11/2024 Approved EUGENE CASSIDY
Drywall Nailing 7/10/2024 Approved EUGENE CASSIDY
Service/Power Release 8/2/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 12/4/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 12/4/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 12/4/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/10/2025 Corrections Issued EUGENE CASSIDY
HVAC-Final 4/10/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/17/2025 Corrections Issued EUGENE CASSIDY
Final 2/9/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 2/9/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/9/2026 Approved EUGENE CASSIDY