1507 W TORRANCE BLVD 90501
Certificate Information: 1507 W TORRANCE BLVD 90501
- Application / Permit
- 21014-10000-02797
- Plan Check / Job No.
- B21LA10470
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION AND STRUCTURAL INTERIOR REMODEL TO EXISTING 1-STORY SFD
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- Issued on 5/12/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/27/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 8/5/2021 | JASON HEALEY |
| Building Plans Picked Up | 8/13/2021 | APPLICANT |
| Applicant returned to address corrections | 9/28/2021 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 5/12/2022 | MAHNAZ NOURHASHEMI |
| Issued | 5/12/2022 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 9/8/2021 | JASON SHEETS |
| Low Impact Development | Cleared | 2/28/2022 | ANTHONY VARGAS |
| Address approval | Cleared | 3/2/2022 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/2/2022 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2022 | ERIK BEASLEY |
| Sewer availability | Cleared | 3/21/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shirley,, Peter Franklin; Lic. No.: C75050 | 4429 DAWES AVE CULVER CITY, CA 90230 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/6/2022 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/6/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 2/7/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2023 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/31/2023 | Corrections Issued | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2023 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2024 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 4/4/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 5/1/2024 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 5/1/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/21/2024 | Partial Approval | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 5/21/2024 | Partial Approval | EUGENE CASSIDY |
| Insulation | 6/7/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 6/11/2024 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Approved | EUGENE CASSIDY |
| Green Building Rough | 6/11/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 6/11/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/10/2024 | Approved | EUGENE CASSIDY |
| Service/Power Release | 8/2/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Final | 12/4/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Final | 12/4/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 4/10/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/17/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 2/9/2026 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 2/9/2026 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/9/2026 | Approved | EUGENE CASSIDY |