2607 S BENTLEY AVE 90064

Certificate Information: 2607 S BENTLEY AVE 90064

Application / Permit
21014-10000-02794
Plan Check / Job No.
B21LA10461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED A.D.U. GARAGE CONVERSION AND ADDITION PER LAMC 12.22 A.33(C) and (D).
Permit Issued
Issued on 2/23/2022
Issuing Office
Current Status
CofO Issued on 6/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 LAWRENCE QUIRANTE
Corrections Issued 6/12/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/18/2021 LUKE GONZALES
Applicant returned to address corrections 11/18/2021 RICARDO RAMIREZ
Plan Check Approved 11/18/2021 RICARDO RAMIREZ
Issued 2/23/2022 APPLICANT
Building Plans Picked Up 2/25/2022 APPLICANT
CofO in Progress 6/6/2023 DAVID FEILER
Permit Finaled 6/29/2023 DANIEL ORRANTE
CofO Issued 6/29/2023 DANIEL ORRANTE
Permit Finaled 6/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/12/2021 DINAH GARIN
Specific Plan Cleared 8/13/2021 JASON CHAN
Specific Plan Cleared 10/12/2021 DYLAN SITTIG
Grading Pre-Inspection Cleared 10/13/2021 MATTHEW JENKINS
Eng Process Fee Ord 176,300 Cleared 10/18/2021 DINAH GARIN
Sewer availability Cleared 10/18/2021 DINAH GARIN
Construction near power lines Cleared 10/25/2021 RIDWAN HARDY
Roof/Waste drainage to street Cleared 10/27/2021 DINAH GARIN

Contact Information

Contractor Ram Construction Innovation; Lic. No.: 1064340-B 11664 NATIONAL BLVD #116      LOS ANGELES, CA 90064
Engineer Vahabzadeh,, Reza; Lic. No.: S6538 13961 MOORPARK ST APT 207      SHERMAN OAKS, CA 91423

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 3/23/2022 Approved JOHNNY MIRANDA
Underground Mechanical 3/23/2022 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 4/7/2022 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 4/14/2022 Approved JOHNNY MIRANDA
METHANE-Barrier 4/14/2022 Approved JOHNNY MIRANDA
Green Building Rough 8/29/2022 Partial Inspection JOHN KIDWELL
ELECTRICAL-Rough 8/31/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 8/31/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 8/31/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 9/12/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 9/12/2022 Approved JOHNNY MIRANDA
Green Building Rough 9/12/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 9/12/2022 Approved JOHNNY MIRANDA
MERV13>=Rough 9/12/2022 Approved JOHNNY MIRANDA
METHANE-Rough 9/12/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 9/12/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/21/2022 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 9/23/2022 Approved JOHNNY MIRANDA
Green Building Rough 9/23/2022 Approved JOHNNY MIRANDA
Insulation 9/23/2022 Approved JOHNNY MIRANDA
Drywall Nailing 9/28/2022 Approved JOHN KIDWELL
Shower Pan 9/28/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 9/29/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 5/5/2023 Approved JOHNNY MIRANDA
Final 5/5/2023 Corrections Issued JOHNNY MIRANDA
Green Building Final 5/5/2023 Approved JOHNNY MIRANDA
HVAC-Final 5/5/2023 Approved JOHNNY MIRANDA
MERV13>=Final 5/5/2023 Approved JOHNNY MIRANDA
PLUMBING-Final 5/5/2023 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/5/2023 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 5/5/2023 Approved JOHNNY MIRANDA
Final 5/10/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 5/10/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Approved JOHNNY MIRANDA
Final 5/22/2023 Not Ready for Inspection JOHNNY MIRANDA
Final 6/5/2023 OK to Issue CofO JOHNNY MIRANDA