2607 S BENTLEY AVE 90064
Certificate Information: 2607 S BENTLEY AVE 90064
- Application / Permit
- 21014-10000-02794
- Plan Check / Job No.
- B21LA10461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED A.D.U. GARAGE CONVERSION AND ADDITION PER LAMC 12.22 A.33(C) and (D).
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 6/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/12/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 10/18/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/18/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 11/18/2021 | RICARDO RAMIREZ |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| CofO in Progress | 6/6/2023 | DAVID FEILER |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
| CofO Issued | 6/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2021 | DINAH GARIN |
| Specific Plan | Cleared | 8/13/2021 | JASON CHAN |
| Specific Plan | Cleared | 10/12/2021 | DYLAN SITTIG |
| Grading Pre-Inspection | Cleared | 10/13/2021 | MATTHEW JENKINS |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | DINAH GARIN |
| Sewer availability | Cleared | 10/18/2021 | DINAH GARIN |
| Construction near power lines | Cleared | 10/25/2021 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 10/27/2021 | DINAH GARIN |
Contact Information
| Contractor | Ram Construction Innovation; Lic. No.: 1064340-B | 11664 NATIONAL BLVD #116 LOS ANGELES, CA 90064 |
| Engineer | Vahabzadeh,, Reza; Lic. No.: S6538 | 13961 MOORPARK ST APT 207 SHERMAN OAKS, CA 91423 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Underground Mechanical | 3/23/2022 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 4/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/14/2022 | Approved | JOHNNY MIRANDA |
| METHANE-Barrier | 4/14/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 8/29/2022 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 8/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/31/2022 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 9/12/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 9/12/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/12/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 9/12/2022 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 9/12/2022 | Approved | JOHNNY MIRANDA |
| METHANE-Rough | 9/12/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 9/12/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/23/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 9/23/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 9/23/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 9/28/2022 | Approved | JOHN KIDWELL |
| Shower Pan | 9/28/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Final | 5/5/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/5/2023 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 5/5/2023 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 5/5/2023 | Approved | JOHNNY MIRANDA |
| MERV13>=Final | 5/5/2023 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 5/5/2023 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/5/2023 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 5/5/2023 | Approved | JOHNNY MIRANDA |
| Final | 5/10/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 5/10/2023 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | JOHNNY MIRANDA |
| Final | 5/22/2023 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 6/5/2023 | OK to Issue CofO | JOHNNY MIRANDA |