1012 S BRONSON AVE 90019
Certificate Information: 1012 S BRONSON AVE 90019
- Application / Permit
- 21014-10000-02763
- Plan Check / Job No.
- B21LA10386
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1140 SF DETACHED ADU PER LAMC 12.22 A.33(C) AND (D). ALL WORK PER WFPP
- Permit Issued
- Issued on 1/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/9/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 11/22/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/13/2021 | ADAM HEGAZI |
| Plan Check Approved | 1/7/2022 | JOSEPH RAFOLS |
| Issued | 1/7/2022 | APPLICANT |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| CofO in Progress | 12/28/2022 | JEFFREY MEAD |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
| CofO Issued | 12/31/2022 | DEROLD HAUFF |
| Permit Finaled | 12/31/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2021 | THOMAS LANG |
| Sewer availability | Cleared | 6/24/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2021 | THOMAS LANG |
| HPOZ | Cleared | 8/17/2021 | AMANDA KAINER |
| Low Impact Development | Cleared | 9/24/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/27/2021 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/4/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 2/4/2022 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 2/4/2022 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 2/24/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 3/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Wood Frame | 3/1/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Rough-Elec/Plmb/HVAC | 4/7/2022 | Corrections Issued | STUART CHAPMAN |
| Wood Frame | 4/7/2022 | Corrections Issued | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Partial Approval | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/14/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/22/2022 | Partial Approval | ADAM ESCOTO |
| Insulation | 4/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 4/29/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Insulation | 5/7/2022 | Approved | ALAN MORELOS |
| Drywall Nailing | 5/12/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 5/12/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 6/20/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/20/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 6/20/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/11/2022 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Final | 8/11/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Final | 8/11/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 8/11/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 8/11/2022 | Approved | JEFFREY MEAD |
| METHANE-Final | 8/11/2022 | Approved | JEFFREY MEAD |
| METHANE-Rough | 8/11/2022 | Approved | JEFFREY MEAD |
| Service/Power Release | 8/11/2022 | Corrections Issued | JEFFREY MEAD |
| Smoke Detectors | 8/11/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 8/11/2022 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 8/26/2022 | Partial Approval | JEFFREY MEAD |
| Final | 8/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Final | 8/26/2022 | Approved | JEFFREY MEAD |
| Service/Power Release | 8/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Smoke Detectors | 8/26/2022 | Not Ready for Inspection | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | JEFFREY MEAD |
| Final | 9/20/2022 | Partial Approval | JEFFREY MEAD |
| Service/Power Release | 9/20/2022 | Approved | JEFFREY MEAD |
| Smoke Detectors | 9/20/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 12/27/2022 | Approved | JEFFREY MEAD |
| Final | 12/27/2022 | OK to Issue CofO | JEFFREY MEAD |
| HVAC-Final | 12/27/2022 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 12/27/2022 | Approved | JEFFREY MEAD |