11512 W LA MAIDA ST 91601

Certificate Information: 11512 W LA MAIDA ST 91601

Application / Permit
21014-10000-02751
Plan Check / Job No.
B21LA10336
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND MAJOR INTERIOR REMODEL SFD TO ADD A MASTERS BEDROOM, CREATE 2 BATHS, POWDER ROOM, WINDOW CHANGE OUT, RAISE CEILING, KITCHEN REMODEL.
Permit Issued
Issued on 12/8/2021
Issuing Office
Current Status
CofO Issued on 1/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 LUKE GONZALES
Corrections Issued 6/12/2021 LUKE GONZALES
Applicant returned to address corrections 10/19/2021 FERNANDO FLORES
Applicant returned to address corrections 11/29/2021 ZAW HAN
Plan Check Approved 12/8/2021 RICARDO RAMIREZ
Issued 12/8/2021 APPLICANT
Building Plans Picked Up 12/9/2021 APPLICANT
CofO in Progress 1/13/2023 JACK KARGODORIAN
Permit Finaled 1/24/2023 MICHAEL SMITH
CofO Issued 1/24/2023 MICHAEL SMITH
Permit Finaled 1/24/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2021 CARLOS AGUILERA
Sewer availability Cleared 9/8/2021 CARLOS AGUILERA
Specific Plan Cleared 9/22/2021 CORREY KITCHENS
ZI Cleared 9/22/2021 CORREY KITCHENS
ZI Cleared 9/22/2021 CORREY KITCHENS
Low Impact Development Cleared 11/4/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/8/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/20/2021 Approved THOMAS FINNILA
PLUMBING-Rough 1/24/2022 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 1/27/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/27/2022 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/3/2022 Partial Approval THOMAS FINNILA
Insulation 2/7/2022 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Approval MATT KELLERMAN
Rough-Elec/Plmb/HVAC 4/29/2022 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/29/2022 Not Ready for Inspection THOMAS FINNILA
Rough-Elec/Plmb/HVAC 7/7/2022 Corrections Issued CALEB MEISTER
Sewer 7/7/2022 Approved CALEB MEISTER
Wood Frame 7/7/2022 Partial Approval CALEB MEISTER
Wood Frame 7/14/2022 Corrections Issued THOMAS FINNILA
Wood Frame 7/22/2022 Approved THOMAS FINNILA
Deputy Wood Construction 7/28/2022 Conditional Approval THOMAS FINNILA
Insulation 7/29/2022 Approved THOMAS FINNILA
Drywall Nailing 8/5/2022 Approved THOMAS FINNILA
Green Building Rough 8/5/2022 Approved THOMAS FINNILA
Shower Pan 8/5/2022 Corrections Issued THOMAS FINNILA
Shower Pan 8/10/2022 Conditional Approval THOMAS FINNILA
Shower Pan 8/15/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 9/27/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 12/2/2022 Approved JOHN COLEMAN
Final 12/2/2022 Corrections Issued JOHN COLEMAN
Green Building Final 12/2/2022 Approved JOHN COLEMAN
MERV13>=Final 12/2/2022 Approved JOHN COLEMAN
MERV13>=Rough 12/2/2022 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Not Ready JOHN COLEMAN
Smoke Detectors 12/2/2022 Approved JOHN COLEMAN
Final 12/29/2022 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved JACK KARGODORIAN
Final 1/12/2023 OK to Issue CofO JACK KARGODORIAN