2419 S DUNSMUIR AVE 90016

Certificate Information: 2419 S DUNSMUIR AVE 90016

Application / Permit
21014-10000-02747
Plan Check / Job No.
B21LA10323
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED BEDROOM AND BATHROOM ADDITION AT REAR OF (E) SFD. INCLUDES INTERIOR REMODEL OF (E) PORTIONS OF UNIT.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 8/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 LAWRENCE QUIRANTE
Corrections Issued 6/12/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/7/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/23/2021 LUKE GONZALES
Plan Check Approved 9/8/2021 DANIEL SANJUAN
Issued 9/15/2021 APPLICANT
Building Plans Picked Up 9/17/2021 APPLICANT
CofO in Progress 8/5/2023 JOSE AVILA
Permit Finaled 8/10/2023 DEROLD HAUFF
CofO Issued 8/10/2023 DEROLD HAUFF
Permit Finaled 8/10/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/5/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/9/2021 STEVE MELGAR

Contact Information

Architect Mariam, Mojdehi; Lic. No.: C37992       ,
Contractor Mozannar Construction Inc; Lic. No.: 695817-B 10721 BLOOMFIELD ST #1      NORTH HOLLYWOOD, CA 91602
Engineer Paniagua,, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/29/2021 Conditional Approval JOSE AVILA
Underground Mechanical 10/29/2021 Approved JOSE AVILA
Deputy Drilled-In Anchors 11/8/2021 Conditional Approval JUSTIN HAWLEY
Footing/Foundation/Slab 12/9/2021 Approved JOSE AVILA
Deputy Wood Construction 1/20/2022 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 1/24/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/24/2022 Partial Approval JOSE AVILA
Green Building Rough 1/24/2022 Not Ready for Inspection JOSE AVILA
MERV13>=Rough 1/24/2022 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 2/25/2022 Partial Approval JOSE AVILA
Rough-Elec/Plmb/HVAC 2/25/2022 Approved JOSE AVILA
Insulation 3/9/2022 Approved JOSE AVILA
Drywall Nailing 3/14/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/3/2022 Not Ready for Inspection JOSE AVILA
Drywall Nailing 5/4/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/5/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 12/7/2022 Partial Approval JOSE AVILA
ELECTRICAL-Final 12/7/2022 Corrections Issued JOSE AVILA
Final 12/7/2022 Corrections Issued JOSE AVILA
Green Building Final 12/7/2022 Approved JOSE AVILA
Green Building Rough 12/7/2022 Approved JOSE AVILA
HVAC-Final 12/7/2022 Corrections Issued JOSE AVILA
MERV13>=Final 12/7/2022 Approved JOSE AVILA
MERV13>=Rough 12/7/2022 Conditional Approval JOSE AVILA
PLUMBING-Final 12/7/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 12/7/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 1/17/2023 Approved SCOTT FINNILA
Final 1/17/2023 Partial Inspection SCOTT FINNILA
HVAC-Final 1/17/2023 Corrections Issued SCOTT FINNILA
MERV13>=Rough 1/17/2023 Approved SCOTT FINNILA
Smoke Detectors 1/17/2023 Approved SCOTT FINNILA
HVAC-Final 2/21/2023 Partial Approval JOSE AVILA
Final 6/29/2023 Partial Approval JOSE AVILA
Final 8/5/2023 OK to Issue CofO JOSE AVILA