11510 W LA MAIDA ST 91601
Certificate Information: 11510 W LA MAIDA ST 91601
- Application / Permit
- 21014-10000-02745
- Plan Check / Job No.
- B21LA10319
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU at rear of lot per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 2/23/2022
- Issuing Office
- Current Status
- CofO Issued on 1/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2021 | TSE MING HUANG |
| Plan Check Approved | 2/17/2022 | RICARDO RAMIREZ |
| Issued | 2/23/2022 | APPLICANT |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | JACK KARGODORIAN |
| CofO in Progress | 1/18/2023 | JACK KARGODORIAN |
| CofO in Progress | 1/20/2023 | JACK KARGODORIAN |
| CofO Issued | 1/24/2023 | MICHAEL SMITH |
| Permit Finaled | 1/24/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/19/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/31/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/31/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/19/2021 | JOHN CONNEALLY |
| Specific Plan | Cleared | 9/22/2021 | CORREY KITCHENS |
| Low Impact Development | Cleared | 11/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 11/8/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Hurtado,, Jesus; Lic. No.: C29969 | 1310 S MCDONNELL AVENUE LOS ANGELES, CA 90022 |
| Contractor | Owner-Builder | , |
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/16/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 3/23/2022 | Not Ready for Inspection | DAVID MATSON |
| Special/Order Compliance | 3/25/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/4/2022 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Conditional Approval | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 7/1/2022 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Approved | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 7/7/2022 | Corrections Issued | CALEB MEISTER |
| Sewer | 7/7/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 7/15/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 7/15/2022 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 7/15/2022 | Approved | THOMAS FINNILA |
| Underground Mechanical | 7/15/2022 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 7/15/2022 | Approved | THOMAS FINNILA |
| Insulation | 7/22/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 7/29/2022 | Approved | THOMAS FINNILA |
| Shower Pan | 8/5/2022 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 8/10/2022 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 8/15/2022 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/27/2022 | Approved | WILLIAM WREN |
| Final | 12/2/2022 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 12/2/2022 | Approved | JOHN COLEMAN |
| Green Building Final | 12/2/2022 | Approved | JOHN COLEMAN |
| MERV13>=Final | 12/2/2022 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Not Ready | JOHN COLEMAN |
| Service/Power Release | 12/2/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 12/2/2022 | Approved | JOHN COLEMAN |
| Final | 12/29/2022 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 12/29/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 1/12/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 1/12/2023 | Approved | JACK KARGODORIAN |