345 S HIGHLAND AVE 90036
Certificate Information: 345 S HIGHLAND AVE 90036
- Application / Permit
- 21014-10000-02684
- Plan Check / Job No.
- B21LA10099
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO GARAGE AND CONVERT TO ADU.
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | JOE VO |
| Corrections Issued | 6/17/2021 | JOE VO |
| Plan Check Approved | 10/15/2021 | JOE VO |
| Issued | 11/5/2021 | APPLICANT |
| CofO in Progress | 8/28/2023 | ROY SPAULDING |
| Permit Finaled | 10/9/2024 | RUBEN SALAS |
| CofO Issued | 10/9/2024 | RUBEN SALAS |
| Permit Finaled | 10/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/1/2021 | JEANIE LAM |
| HPOZ | Cleared | 7/22/2021 | SUKI GERSHENHORN |
| Historic monument | Cleared | 7/22/2021 | SUKI GERSHENHORN |
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2021 | JEANIE LAM |
| Sewer availability | Cleared | 10/1/2021 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/25/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/4/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 4/7/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/9/2022 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 1/25/2023 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/1/2023 | Corrections Issued | RICHARD DOCKUS |
| METHANE-Barrier | 2/1/2023 | Approved | RICHARD DOCKUS |
| METHANE-Subgrade | 2/1/2023 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 2/1/2023 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 3/7/2023 | Partial Approval | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 3/15/2023 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 3/21/2023 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/12/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 4/12/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Rough | 4/12/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 4/20/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 4/20/2023 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/20/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Rough | 5/5/2023 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 5/5/2023 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 5/5/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 5/16/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/24/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 6/5/2023 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 6/12/2023 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 6/22/2023 | Approved | RICHARD DOCKUS |
| Shower Pan | 6/22/2023 | Approved | RICHARD DOCKUS |
| Final | 6/29/2023 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/29/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 8/25/2023 | Approved | ROY SPAULDING |
| Final | 8/25/2023 | OK to Issue CofO | ROY SPAULDING |
| HVAC-Final | 8/25/2023 | Approved | ROY SPAULDING |
| PLUMBING-Final | 8/25/2023 | Approved | ROY SPAULDING |