345 S HIGHLAND AVE 90036

Certificate Information: 345 S HIGHLAND AVE 90036

Application / Permit
21014-10000-02684
Plan Check / Job No.
B21LA10099
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO GARAGE AND CONVERT TO ADU.
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 10/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 JOE VO
Corrections Issued 6/17/2021 JOE VO
Plan Check Approved 10/15/2021 JOE VO
Issued 11/5/2021 APPLICANT
CofO in Progress 8/28/2023 ROY SPAULDING
Permit Finaled 10/9/2024 RUBEN SALAS
CofO Issued 10/9/2024 RUBEN SALAS
Permit Finaled 10/9/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/1/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 7/1/2021 JEANIE LAM
HPOZ Cleared 7/22/2021 SUKI GERSHENHORN
Historic monument Cleared 7/22/2021 SUKI GERSHENHORN
Construction near power lines Cleared 9/13/2021 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/1/2021 JEANIE LAM
Sewer availability Cleared 10/1/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 4/4/2022 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 4/7/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 5/9/2022 Approved ARTHUR SARGSYAN
Pre-Inspection 1/25/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 2/1/2023 Corrections Issued RICHARD DOCKUS
METHANE-Barrier 2/1/2023 Approved RICHARD DOCKUS
METHANE-Subgrade 2/1/2023 Approved RICHARD DOCKUS
Underground Mechanical 2/1/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 3/7/2023 Partial Approval RICHARD DOCKUS
Deputy Drilled-In Anchors 3/15/2023 Conditional Approval MICHAEL LEWIS
Footing/Foundation/Slab 3/21/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 4/12/2023 Not Ready for Inspection RICHARD DOCKUS
ELECTRICAL-Rough 4/12/2023 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 4/12/2023 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 4/20/2023 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/20/2023 Approved ALIZAH MAYAGOITIA
METHANE-Rough 4/20/2023 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 4/20/2023 Corrections Issued ALIZAH MAYAGOITIA
HVAC-Rough 5/5/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 5/5/2023 Approved RICHARD DOCKUS
Underground Mechanical 5/5/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 5/16/2023 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/24/2023 Approved RICHARD DOCKUS
Drywall Nailing 6/5/2023 Approved RICHARD DOCKUS
Drywall Nailing 6/12/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/22/2023 Approved RICHARD DOCKUS
Shower Pan 6/22/2023 Approved RICHARD DOCKUS
Final 6/29/2023 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 6/29/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 8/25/2023 Approved ROY SPAULDING
Final 8/25/2023 OK to Issue CofO ROY SPAULDING
HVAC-Final 8/25/2023 Approved ROY SPAULDING
PLUMBING-Final 8/25/2023 Approved ROY SPAULDING