5410 W CLINTON ST 90004
Certificate Information: 5410 W CLINTON ST 90004
- Application / Permit
- 21014-10000-02680
- Plan Check / Job No.
- B21LA10097
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. ADU CONVERSION AND ADDITION TO AN EXISTING DETACHED GARAGE PER GCS 65852.2(e)(1)(A). All work per Engineer Design.
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2021 | ZAW HAN |
| Corrections Issued | 6/8/2021 | ZAW HAN |
| Plan Check Approved | 9/30/2021 | ZAW HAN |
| Issued | 10/13/2021 | APPLICANT |
| CofO in Progress | 12/12/2022 | JOSEPH MCGARRY |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
| CofO Issued | 12/17/2022 | DEROLD HAUFF |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/13/2021 | RIDWAN HARDY |
| CPC | Cleared | 9/14/2021 | TERRI OSBORNE |
| CPC | Cleared | 9/14/2021 | TERRI OSBORNE |
| Address approval | Cleared | 9/17/2021 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/22/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/22/2021 | JEANIE LAM |
Contact Information
| Architect | Cho,, Leo D; Lic. No.: C25658 | 5500 HOLLYWOOD BLVD #301 LOS ANGELES, CA 90028 |
| Contractor | Owner-Builder | , |
| Engineer | Reppuhn,, Nikolaus Yong Bok; Lic. No.: C83924 | 1205 DUNNING WAY SAN DIMAS, CA 91773 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2021 | Approved | MASHEL JONGERT |
| METHANE-Barrier | 12/1/2021 | Approved | MASHEL JONGERT |
| METHANE-Subgrade | 12/1/2021 | Approved | MASHEL JONGERT |
| ELECTRICAL-Rough | 3/25/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 3/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Insulation | 3/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/25/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 3/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Wood Frame | 3/25/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 5/13/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 5/13/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 6/16/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 6/16/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 6/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| Insulation | 7/15/2022 | Approved | JEFFREY MEAD |
| METHANE-Rough | 7/15/2022 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/26/2022 | Approved | JEFFREY MEAD |
| METHANE-Rough | 7/26/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/10/2022 | Approved | JEFFREY MEAD |
| Green Building Rough | 8/15/2022 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/15/2022 | Approved | JEFFREY MEAD |
| Final | 11/30/2022 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV No Gas | JEFFREY MEAD |
| Smoke Detectors | 11/30/2022 | Approved | JEFFREY MEAD |
| Final | 12/9/2022 | OK to Issue CofO | JOSEPH MCGARRY |