6618 W MELROSE AVE 90038
Certificate Information: 6618 W MELROSE AVE 90038
- Application / Permit
- 21014-10000-02635
- Plan Check / Job No.
- B21LA09957
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TI ON (E) RETAIL SPACE & NEW ADDITION W/(N) ELEVATOR, (N) SECOND FLOOR OFFICES W/ROOFDECK, (N) PARKING AREA
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Current Status
- CofO Issued on 7/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 7/15/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 7/28/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 2/3/2022 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 4/12/2022 | ARSALAN SHABESTARI |
| Issued | 4/12/2022 | APPLICANT |
| Building Plans Picked Up | 4/14/2022 | APPLICANT |
| CofO in Progress | 4/19/2024 | MARTIN TAVITIAN |
| CofO Issued | 7/15/2024 | ERNESTO CORRAL |
| Permit Finaled | 7/15/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | RENZ SORIANO |
| Address approval | Cleared | 8/30/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/30/2021 | RENZ SORIANO |
| Tract Map conditions | Cleared | 9/1/2021 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/1/2021 | RUBEN VASQUEZ |
| Hydrant and Access approval | Cleared | 10/2/2021 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 10/12/2021 | SAM NAVID |
| Highway dedication | Cleared | 10/15/2021 | RENZ SORIANO |
| Construction near power lines | Cleared | 11/18/2021 | OSCAR CASTRO |
| Construction within easement | Cleared | 11/18/2021 | OSCAR CASTRO |
| Green Code | Cleared | 1/20/2022 | ARSALAN SHABESTARI |
| Low Impact Development | Cleared | 1/26/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | JEANETTE VONG |
| DAS Clearance | Cleared | 3/1/2022 | ARSALAN SHABESTARI |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Calasia Construction Inc; Lic. No.: 938255-B | 3050 FLETCHER DRIVE LOS ANGELES, CA 90065 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2022 | Approved | KATY RAMIREZ |
| Grading Pre-Inspection | 4/26/2022 | Corrections Issued | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 8/18/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 8/24/2022 | Conditional Approval | WINSTON DUNNING |
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | WINSTON DUNNING |
| Excavation/Setback/Form/Re-Bar | 9/7/2022 | Partial Approval | GREGORY POMISH |
| Deputy Reinf. Concrete | 9/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 9/16/2022 | Partial Approval | KATY RAMIREZ |
| METHANE-Barrier | 9/16/2022 | Not Ready for Inspection | KATY RAMIREZ |
| METHANE-Subgrade | 9/16/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Deputy Reinf. Concrete | 9/21/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 10/6/2022 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 10/6/2022 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Subgrade | 10/6/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/13/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 10/17/2022 | Partial Approval | KATY RAMIREZ |
| METHANE-Barrier | 10/17/2022 | Partial Approval | KATY RAMIREZ |
| METHANE-Subgrade | 10/17/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Methane Barrier | 11/4/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 11/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 11/7/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 11/15/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 11/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 11/16/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 12/5/2022 | Partial Approval | EDWIN GREGORYONA |
| METHANE-Barrier | 12/5/2022 | Partial Inspection | EDWIN GREGORYONA |
| METHANE-Subgrade | 12/5/2022 | Partial Inspection | EDWIN GREGORYONA |
| Reinforced Concrete Frame | 12/8/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 12/9/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 1/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 1/10/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 1/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 1/10/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 1/18/2023 | Approved | JEROME BLACKWOOD |
| Structural Steel Frame | 1/18/2023 | Approved | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Barrier | 1/26/2023 | Conditional Approval | JEROME BLACKWOOD |
| METHANE-Subgrade | 1/26/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Reinf. Concrete | 1/27/2023 | Approved | JEROME BLACKWOOD |
| Drywall Nailing | 1/27/2023 | Order to Comply Issued | JEROME BLACKWOOD |
| Drywall Nailing | 1/31/2023 | Partial Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2023 | Partial Approval | TED RIES |
| Special/Order Compliance | 1/31/2023 | Approved | TED RIES |
| Deputy Reinf. Masonry | 2/6/2023 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 2/7/2023 | Partial Approval | JEROME BLACKWOOD |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | JEROME BLACKWOOD |
| Pre-Inspection | 2/9/2023 | Partial Inspection | JEROME BLACKWOOD |
| Special/Order Compliance | 2/9/2023 | Approved | EDWIN GREGORYONA |
| Light Gage Steel Frame | 3/7/2023 | Partial Approval | RONALD JIMENEZ |
| Masonry Wall/Backfill | 3/7/2023 | Partial Approval | RONALD JIMENEZ |
| Deputy Reinf. Masonry | 3/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Drywall Nailing | 3/17/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Subgrade | 3/28/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Final | 4/18/2023 | Conditional Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 4/24/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Barrier | 4/24/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Subgrade | 4/24/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Methane Barrier | 4/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 4/26/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 5/3/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 5/3/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 5/3/2023 | Partial Inspection | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2023 | Partial Approval | JEROME BLACKWOOD |
| Deputy Steel/Welding | 5/30/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Green Building Rough | 6/9/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wall Anchors | 6/9/2023 | Approved | JEROME BLACKWOOD |
| Wood Frame | 6/9/2023 | Partial Approval | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/30/2023 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2023 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 6/30/2023 | Partial Approval | RONALD JIMENEZ |
| METHANE-Barrier | 6/30/2023 | Partial Inspection | RONALD JIMENEZ |
| METHANE-Subgrade | 6/30/2023 | Partial Inspection | RONALD JIMENEZ |
| Drywall Nailing | 7/25/2023 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Partial Approval | RONALD JIMENEZ |
| Green Building Rough | 7/25/2023 | Approved | RONALD JIMENEZ |
| Insulation | 7/25/2023 | Partial Approval | RONALD JIMENEZ |
| Wood Frame | 7/25/2023 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 8/1/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Barrier | 8/1/2023 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Subgrade | 8/1/2023 | Approved | JEROME BLACKWOOD |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/18/2023 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2023 | Approved | RONALD JIMENEZ |
| Insulation | 8/18/2023 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 8/30/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 9/12/2023 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 9/19/2023 | Partial Approval | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 9/27/2023 | Conditional Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 9/28/2023 | Partial Approval | JEROME BLACKWOOD |
| Structural Steel Frame | 9/28/2023 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/12/2023 | Partial Approval | JACOB MYERS |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | JACOB MYERS |
| Pre-Inspection | 2/15/2024 | Partial Inspection | GREGORY POMISH |
| Final | 4/2/2024 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 4/2/2024 | Approved | MARTIN TAVITIAN |
| Green Building Final | 4/2/2024 | Approved | MARTIN TAVITIAN |
| METHANE-Barrier | 4/2/2024 | Approved | MARTIN TAVITIAN |
| Reinforced Masonry Frame | 4/2/2024 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 4/2/2024 | Approved | MARTIN TAVITIAN |
| Wood Frame | 4/2/2024 | Approved | MARTIN TAVITIAN |
| Final | 4/17/2024 | OK to Issue CofO | MARTIN TAVITIAN |