2498 S COLBY AVE 90064
Certificate Information: 2498 S COLBY AVE 90064
- Application / Permit
- 21014-10000-02630
- Plan Check / Job No.
- B21LA09942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 182 SF ADDITION TO A SFD FOR BEDROOM AND KITCHEN EXTENSION. COMPLETE KITCHEN REMODEL WITH ENGINEER DESIGN
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2021 | ZAW HAN |
| Corrections Issued | 6/1/2021 | ZAW HAN |
| Plan Check Approved | 7/5/2021 | LUKE GONZALES |
| Plan Check Approved | 7/8/2021 | LUKE GONZALES |
| Issued | 7/14/2021 | APPLICANT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| CofO in Progress | 4/15/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
| CofO Issued | 4/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 6/9/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 6/9/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 6/14/2021 | VALERIA CEJA |
| CPC | Cleared | 6/21/2021 | DENZEL HENDERSON |
| Specific Plan | Cleared | 6/21/2021 | DENZEL HENDERSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/12/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/13/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/23/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/31/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/31/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 9/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 9/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 9/2/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 9/17/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2021 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 11/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| MERV13>=Rough | 11/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 11/9/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/23/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/23/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/23/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/29/2021 | Approved | EVAN COOPER |
| HVAC-Rough | 11/29/2021 | Approved | EVAN COOPER |
| Insulation | 11/29/2021 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 11/29/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 12/2/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Rough | 12/2/2021 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/2/2021 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 12/2/2021 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/7/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 4/14/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Rough | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 4/14/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/14/2022 | Approved | OGANES TARAKHCHYAN |