410 S HIGHLAND AVE 90036

Certificate Information: 410 S HIGHLAND AVE 90036

Application / Permit
21014-10000-02624
Plan Check / Job No.
B21LA09910
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW TWO STORY ADU WITH GARAGE AT 1ST LEVEL.
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
Issued on 10/27/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 JOE VO
Corrections Issued 6/19/2021 JOE VO
Quality Review Completed 6/24/2021 MICHAEL PEREZ
Plan Check Approved 10/19/2021 JOE VO
Issued 10/27/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/26/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 7/26/2021 CECILIO NAVARRO
HPOZ Cleared 8/31/2021 SUKI GERSHENHORN
Historic monument Cleared 8/31/2021 SUKI GERSHENHORN
Sewer availability Cleared 9/10/2021 CECILIO NAVARRO
Construction near power lines Cleared 9/14/2021 WALTER RAMIREZ
Hydrant and Access approval Cleared 9/17/2021 KURT CORRAL
Low Impact Development Cleared 9/24/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/30/2021 WALLIE JONG

Contact Information

Architect Eckelberry,, Anthony Evans; Lic. No.: NA17278       ,
Contractor Owner-Builder       ,
Engineer Avila,, Albert Guerrero; Lic. No.: NA41726       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 12/14/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 12/14/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 12/21/2021 Partial Approval ARTHUR SARGSYAN
METHANE-Barrier 12/21/2021 Partial Approval ARTHUR SARGSYAN
METHANE-Subgrade 12/21/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 1/4/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 1/4/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 1/4/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/11/2022 Partial Approval ARTHUR SARGSYAN
Drywall Nailing 1/28/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Approved ARTHUR SARGSYAN
Deputy Wood Construction 2/8/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 2/17/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 2/17/2022 Approved ARTHUR SARGSYAN
Shower Pan 2/17/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/24/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 2/24/2022 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 2/24/2022 Approved ARTHUR SARGSYAN
Insulation 3/1/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 3/8/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 3/8/2022 Approved ARTHUR SARGSYAN
Sewer 7/5/2022 Partial Approval ADAM ESCOTO
Sewer 7/7/2022 Approved ADAM ESCOTO
Service/Power Release 2/27/2024 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Final 2/29/2024 Corrections Issued RICHARD DOCKUS
Footing/Foundation/Slab 2/29/2024 Approved RICHARD DOCKUS
METHANE-Barrier 2/29/2024 Approved RICHARD DOCKUS
Smoke Detectors 2/29/2024 Approved RICHARD DOCKUS
ELECTRICAL-Final 3/11/2024 Not Ready for Inspection RONNIE MINDANAO
Final 3/11/2024 Corrections Issued RONNIE MINDANAO
Underground Mechanical 3/11/2024 Approved RONNIE MINDANAO
Final 4/4/2024 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 4/4/2024 SGSOV Not Ready RONNIE MINDANAO
Service/Power Release 4/4/2024 Not Ready for Inspection RONNIE MINDANAO
Service/Power Release 4/24/2024 Corrections Issued RONNIE MINDANAO
Service/Power Release 4/29/2024 Not Ready for Inspection ROY SPAULDING
Service/Power Release 4/30/2024 Approved JOAQUIN GREENOUGH
Verify Rec and Parks Fee Memo 5/14/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 3/12/2026 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved RONNIE MINDANAO