410 S HIGHLAND AVE 90036
Certificate Information: 410 S HIGHLAND AVE 90036
- Application / Permit
- 21014-10000-02624
- Plan Check / Job No.
- B21LA09910
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ADU WITH GARAGE AT 1ST LEVEL.
- Permit Issued
- Issued on 10/27/2021
- Issuing Office
- Current Status
- Issued on 10/27/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | JOE VO |
| Corrections Issued | 6/19/2021 | JOE VO |
| Quality Review Completed | 6/24/2021 | MICHAEL PEREZ |
| Plan Check Approved | 10/19/2021 | JOE VO |
| Issued | 10/27/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/26/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2021 | CECILIO NAVARRO |
| HPOZ | Cleared | 8/31/2021 | SUKI GERSHENHORN |
| Historic monument | Cleared | 8/31/2021 | SUKI GERSHENHORN |
| Sewer availability | Cleared | 9/10/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 9/14/2021 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 9/17/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 9/24/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | WALLIE JONG |
Contact Information
| Architect | Eckelberry,, Anthony Evans; Lic. No.: NA17278 | , |
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: NA41726 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 12/14/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 12/21/2021 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 12/21/2021 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Subgrade | 12/21/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 1/4/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/4/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/4/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Partial Approval | ARTHUR SARGSYAN |
| Drywall Nailing | 1/28/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Wood Construction | 2/8/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/17/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2022 | Partial Approval | ARTHUR SARGSYAN |
| PLUMBING-Rough | 2/17/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 2/17/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Verify Sprinkler Sign Off | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 3/1/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 3/8/2022 | Approved | ARTHUR SARGSYAN |
| Sewer | 7/5/2022 | Partial Approval | ADAM ESCOTO |
| Sewer | 7/7/2022 | Approved | ADAM ESCOTO |
| Service/Power Release | 2/27/2024 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 2/29/2024 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 2/29/2024 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 2/29/2024 | Approved | RICHARD DOCKUS |
| Smoke Detectors | 2/29/2024 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 3/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 3/11/2024 | Corrections Issued | RONNIE MINDANAO |
| Underground Mechanical | 3/11/2024 | Approved | RONNIE MINDANAO |
| Final | 4/4/2024 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Service/Power Release | 4/4/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Service/Power Release | 4/24/2024 | Corrections Issued | RONNIE MINDANAO |
| Service/Power Release | 4/29/2024 | Not Ready for Inspection | ROY SPAULDING |
| Service/Power Release | 4/30/2024 | Approved | JOAQUIN GREENOUGH |
| Verify Rec and Parks Fee Memo | 5/14/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 3/12/2026 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 3/12/2026 | SGSOV Approved | RONNIE MINDANAO |