1037 W 65TH PL 90044

Certificate Information: 1037 W 65TH PL 90044

Application / Permit
21014-10000-02617
Plan Check / Job No.
B21LA09882
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT [11 X 20] DETACHED GARAGE TO 2 BEDROOM, 1 BATH ADU. WITH 1-STORY [29 X 21] ADDITION TO WEST SIDE. PROVIDE TWO OPEN PARKING SPACES WITH SOLID FENCE SCREEN.
Permit Issued
Issued on 3/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 FARSHAD ALIMOHAMADI
Corrections Issued 6/10/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 3/7/2022 JESSE JIMENEZ
Issued 3/29/2022 APPLICANT
Building Plans Picked Up 3/30/2022 APPLICANT
CofO in Progress 11/29/2023 JOHN PARKER
CofO in Progress 11/29/2023 JOHN PARKER
Permit Finaled 7/20/2024 CLAUDIO MORENO
CofO Issued 7/20/2024 CLAUDIO MORENO
Permit Finaled 7/20/2024 CLAUDIO MORENO

Permit Application Clearance Information

Low Impact Development Cleared 10/27/2021 ANTHONY VARGAS
Address approval Cleared 11/5/2021 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 11/5/2021 JEANETTE VONG
Roof/Waste drainage to street Cleared 11/5/2021 JEANETTE VONG
Sewer availability Cleared 11/5/2021 JEANETTE VONG
Construction near power lines Cleared 2/15/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/19/2022 Approved ANDEY CHAPARRO
Excavation/Setback/Form/Re-Bar 5/17/2022 Corrections Issued ANDEY CHAPARRO
Footing/Foundation/Slab 5/17/2022 Not Ready for Inspection ANDEY CHAPARRO
Sewer 5/17/2022 Corrections Issued ANDEY CHAPARRO
ELECTRICAL-Rough 12/27/2022 Approved DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 12/27/2022 Approved DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval DANIEL GONZALEZ
BUILDING-Rough-Frame 1/30/2023 Approved DANIEL GONZALEZ
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Approved DANIEL GONZALEZ
Green Building Rough 1/30/2023 Approved DANIEL GONZALEZ
Insulation 2/9/2023 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 2/9/2023 Partial Approval DANIEL GONZALEZ
Drywall Nailing 3/22/2023 Partial Approval DANIEL GONZALEZ
Drywall Nailing 5/2/2023 Corrections Issued ENRIQUE PREZA
Footing/Foundation/Slab 5/30/2023 Approved JOHN PARKER
Interior/Exterior Lathing 5/30/2023 Approved JOHN PARKER
Gas Test 7/26/2023 Approved JOHN PARKER
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved JOHN PARKER
Service/Power Release 7/26/2023 Approved JOHN PARKER
Sewer 7/26/2023 Approved JOHN PARKER
Service/Power Release 9/13/2023 Approved JOHN PARKER
ELECTRICAL-Final 10/5/2023 Approved JOHN PARKER
Final 10/5/2023 Corrections Issued JOHN PARKER
Green Building Final 10/5/2023 Approved JOHN PARKER
HVAC-Final 10/5/2023 Approved JOHN PARKER
PLUMBING-Final 10/5/2023 Approved JOHN PARKER
Smoke Detectors 10/5/2023 Approved JOHN PARKER
Final 11/29/2023 OK to Issue CofO JOHN PARKER