4852 N TOWNSEND AVE 90041
Certificate Information: 4852 N TOWNSEND AVE 90041
- Application / Permit
- 21014-10000-02612
- Plan Check / Job No.
- B21LA09856
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION (843 SF) TO (E) GARAGE (348 SF) AND CONVERT TO ADU PER LAMC 12.22 A.33(c)-(d) WITH ATTACHED LAUNDRY ROOM (64 SF).
- Permit Issued
- Issued on 3/11/2022
- Issuing Office
- Current Status
- CofO Issued on 3/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | VIVIAN LAO |
| Corrections Issued | 7/8/2021 | VIVIAN LAO |
| Quality Review Completed | 7/19/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 2/1/2022 | VIVIAN LAO |
| Plan Check Approved | 2/17/2022 | VIVIAN LAO |
| Issued | 3/11/2022 | APPLICANT |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| CofO in Progress | 2/10/2023 | CRAIG VAUGHAN |
| Permit Finaled | 3/19/2023 | DEROLD HAUFF |
| CofO Issued | 3/19/2023 | DEROLD HAUFF |
| Permit Finaled | 3/19/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/27/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | WALLIE JONG |
| Sewer availability | Cleared | 8/31/2021 | WALLIE JONG |
| Low Impact Development | Cleared | 1/6/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 1/10/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 2/17/2022 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 2/17/2022 | VIVIAN LAO |
Contact Information
| Contractor | United Construction Group Inc; Lic. No.: 1077065-B | 14545 FRIAR ST VAN NUYS, CA 91411 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/23/2022 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/12/2022 | Partial Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 5/18/2022 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/31/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/6/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/15/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/18/2022 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/18/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/18/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/18/2022 | Approved | CRAIG VAUGHAN |
| Deputy Wood Construction | 8/23/2022 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/30/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/30/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | CRAIG VAUGHAN |
| Insulation | 9/2/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/2/2022 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 9/7/2022 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 9/12/2022 | Approved | BRIAN SULLIVAN |
| Shower Pan | 9/22/2022 | Approved | CRAIG VAUGHAN |
| Gas Test | 10/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 10/28/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Final | 11/29/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 11/29/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Sewer | 11/29/2022 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 11/29/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Rough | 12/7/2022 | Approved | CRAIG VAUGHAN |
| Sewer | 12/7/2022 | Approved | CRAIG VAUGHAN |
| Final | 1/4/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 1/4/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 1/4/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/6/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Gas Test | 1/13/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/13/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/13/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 1/26/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 1/31/2023 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 2/9/2023 | Approved | CRAIG VAUGHAN |
| Final | 2/9/2023 | OK to Issue CofO | CRAIG VAUGHAN |