2724 3/4 E LANFRANCO ST 90033

Certificate Information: 2724 3/4 E LANFRANCO ST 90033

Application / Permit
21014-10000-02603
Plan Check / Job No.
B21LA09805
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF (987 SF) ADU TO EXISTING DETACHED GARAGE. PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 7/7/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 VIVIAN LAO
Corrections Issued 7/12/2021 VIVIAN LAO
Quality Review Completed 7/28/2021 MICHAEL PEREZ
Building Plans Picked Up 8/3/2021 APPLICANT
Applicant returned to address corrections 1/18/2023 VIVIAN LAO
Applicant returned to address corrections 3/14/2023 VIVIAN LAO
Applicant returned to address corrections 4/27/2023 VIVIAN LAO
Plan Check Approved 6/22/2023 VIVIAN LAO
Issued 7/7/2023 APPLICANT
CofO in Progress 12/12/2024 JOHN QUINTANILLA
No Progress 2/2/2025 DEROLD HAUFF
CofO in Progress 2/2/2025 DEROLD HAUFF
Permit Finaled 2/5/2025 DEROLD HAUFF
CofO Issued 2/5/2025 DEROLD HAUFF
Permit Finaled 2/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/13/2021 JOSE HERNANDEZ
Grading Pre-Inspection Cleared 1/21/2022 VASIL MIHALEV
Hydrant and Access approval Cleared 3/8/2022 LARRY REDDEN
Low Impact Development Cleared 10/12/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/26/2022 THAN WIN
Eng Process Fee Ord 176,300 Cleared 5/13/2023 STEVE MELGAR
Sewer availability Cleared 5/13/2023 STEVE MELGAR
GPI Written Notices Cleared 6/13/2023 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/11/2023 Corrections Issued BRENDAN MORELLI
METHANE-Barrier 8/11/2023 Approved BRENDAN MORELLI
METHANE-Subgrade 8/11/2023 Approved BRENDAN MORELLI
Deputy Drilled-In Anchors 8/15/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 8/17/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/28/2023 Partial Inspection FREDDIE RIVERA
Green Building Rough 8/28/2023 Partial Inspection FREDDIE RIVERA
Insulation 8/28/2023 Partial Approval FREDDIE RIVERA
METHANE-Rough 8/28/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 8/28/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 10/2/2023 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/12/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/16/2023 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 10/16/2023 Approved FREDDIE RIVERA
Green Building Rough 10/16/2023 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/19/2023 Approved FREDDIE RIVERA
Wood Frame 10/19/2023 Partial Inspection FREDDIE RIVERA
Drywall Nailing 10/26/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/30/2023 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 11/8/2023 Corrections Issued FREDDIE RIVERA
Shower Pan 11/15/2023 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 11/28/2023 Approved FREDDIE RIVERA
Underground Mechanical 12/7/2023 Partial Approval FREDDIE RIVERA
Sewer 12/13/2023 Partial Approval FREDDIE RIVERA
Sewer 12/18/2023 Approved FREDDIE RIVERA
Final 1/17/2024 Corrections Issued FREDDIE RIVERA
Green Building Final 1/17/2024 Partial Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 1/17/2024 Approved FREDDIE RIVERA
Pre-Inspection 1/31/2024 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Final 9/16/2024 Approved FREDDIE RIVERA
Final 9/16/2024 Partial Inspection FREDDIE RIVERA
Green Building Final 9/16/2024 Approved FREDDIE RIVERA
HVAC-Final 9/16/2024 Approved FREDDIE RIVERA
PLUMBING-Final 9/16/2024 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Approved FREDDIE RIVERA
Service/Power Release 9/16/2024 Approved FREDDIE RIVERA
Final 12/11/2024 OK to Issue CofO JOHN QUINTANILLA