4706 E BUTTERFLY LANE 90032

Certificate Information: 4706 E BUTTERFLY LANE 90032

Application / Permit
21014-10000-02595
Plan Check / Job No.
B21LA09756
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Conversion of an (E) attached garage into an ADU per ordinance 186,481. Remodel (E) SFD.
Permit Issued
Issued on 9/19/2021
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 HELEN NGUYEN
Corrections Issued 5/26/2021 HELEN NGUYEN
Applicant returned to address corrections 7/29/2021 CARLOS MONTES
Plan Check Approved 8/27/2021 CARLOS MONTES
Issued 9/19/2021 APPLICANT
CofO in Progress 1/12/2023 AMY COLIN
Permit Finaled 1/19/2023 DEROLD HAUFF
CofO Issued 1/19/2023 DEROLD HAUFF
Permit Finaled 1/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/3/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 6/3/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 6/3/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 6/3/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 6/3/2021 WALLIE JONG
BHO/Hillside ordinance Cleared 6/3/2021 WALLIE JONG
Sewer availability Cleared 6/3/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/4/2021 WALLIE JONG
Grading Pre-Inspection Cleared 6/30/2021 BRIAN MILLER
"Q" conditions Cleared 7/1/2021 OLGA RUANO
"D" conditions Cleared 7/15/2021 RUBEN VASQUEZ
Tenant Habitability Plan Cleared 7/27/2021 MICHAEL SOTO

Contact Information

Contractor Green Living Remodeling Corp; Lic. No.: 617148-B       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/6/2021 Partial Inspection COREY HUPP
Footing/Foundation/Slab 10/12/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/14/2021 Partial Inspection AMY COLIN
Special/Order Compliance 10/14/2021 Approved RUBEN SALAS
Pre-Inspection 12/20/2021 Partial Inspection COREY HUPP
BUILDING-Rough-Frame 12/23/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 1/3/2022 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 1/19/2022 Partial Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 1/26/2022 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 1/26/2022 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 2/4/2022 Partial Approval COREY HUPP
Rough-Elec/Plmb/HVAC 2/4/2022 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 2/14/2022 Partial Approval OSVALDO PARAMO
ELECTRICAL-Rough 2/14/2022 Corrections Issued OSVALDO PARAMO
HVAC-Rough 2/14/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 2/14/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/18/2022 Partial Approval RUBEN SALAS
Insulation 2/23/2022 Conditional Approval RUBEN SALAS
Pre-Inspection 3/3/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 3/18/2022 Approved AMY COLIN
BUILDING-Rough-Frame 4/19/2022 Not Ready for Inspection RUBEN SALAS
Drywall Nailing 4/19/2022 Not Ready for Inspection RUBEN SALAS
ELECTRICAL-Final 4/19/2022 Not Ready for Inspection RUBEN SALAS
Final 4/19/2022 Not Ready for Inspection RUBEN SALAS
HVAC-Final 4/19/2022 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 4/19/2022 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 4/19/2022 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 4/21/2022 No Access for Inspection AMY COLIN
Drywall Nailing 4/21/2022 No Access for Inspection AMY COLIN
ELECTRICAL-Final 4/21/2022 No Access for Inspection AMY COLIN
HVAC-Final 4/21/2022 No Access for Inspection AMY COLIN
PLUMBING-Final 4/21/2022 No Access for Inspection AMY COLIN
Smoke Detectors 4/21/2022 No Access for Inspection AMY COLIN
Final 4/22/2022 Corrections Issued AMY COLIN
ELECTRICAL-Final 4/26/2022 Not Ready for Inspection RUBEN SALAS
HVAC-Final 4/26/2022 Not Ready for Inspection RUBEN SALAS
PLUMBING-Final 4/26/2022 Not Ready for Inspection RUBEN SALAS
BUILDING-Rough-Frame 4/28/2022 Approved AMY COLIN
Drywall Nailing 4/28/2022 Partial Inspection AMY COLIN
ELECTRICAL-Final 4/28/2022 Approved AMY COLIN
Final 4/28/2022 Partial Inspection AMY COLIN
Gas Test 4/28/2022 Approved AMY COLIN
HVAC-Final 4/28/2022 Approved AMY COLIN
PLUMBING-Final 4/28/2022 Approved AMY COLIN
Smoke Detectors 4/28/2022 Approved AMY COLIN
Drywall Nailing 1/12/2023 Approved AMY COLIN
Final 1/12/2023 OK to Issue CofO AMY COLIN