6111 E MYOSOTIS ST 90042

Certificate Information: 6111 E MYOSOTIS ST 90042

Application / Permit
21014-10000-02586
Plan Check / Job No.
B21LA09745
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Ground addition to rear of an (E) detached garage and conversion of entire building into an ADU per ordinance 186,481.
Permit Issued
Issued on 10/13/2021
Issuing Office
Current Status
CofO Issued on 8/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 HELEN NGUYEN
Corrections Issued 5/26/2021 HELEN NGUYEN
Applicant returned to address corrections 7/8/2021 HELEN NGUYEN
Applicant returned to address corrections 7/30/2021 HELEN NGUYEN
Applicant returned to address corrections 8/3/2021 HELEN NGUYEN
Plan Check Approved 8/10/2021 HELEN NGUYEN
Issued 10/13/2021 APPLICANT
CofO in Progress 8/8/2022 CRAIG VAUGHAN
CofO in Progress 8/8/2022 CRAIG VAUGHAN
Permit Finaled 8/11/2022 DEROLD HAUFF
CofO Issued 8/11/2022 DEROLD HAUFF
Permit Finaled 8/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/29/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 6/29/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 6/29/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 6/29/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 6/29/2021 JEANIE LAM
BHO/Hillside ordinance Cleared 6/29/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 6/29/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 6/29/2021 JEANIE LAM
Sewer availability Cleared 6/29/2021 JEANIE LAM
Grading Pre-Inspection Cleared 7/22/2021 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/28/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 12/28/2021 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 12/28/2021 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 1/7/2022 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 1/25/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/10/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 3/10/2022 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 3/14/2022 Approved SCOTT FINNILA
BUILDING-Rough-Frame 4/8/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 4/8/2022 Approved CRAIG VAUGHAN
Green Building Rough 4/8/2022 Approved CRAIG VAUGHAN
HVAC-Rough 4/8/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 4/8/2022 Approved CRAIG VAUGHAN
Insulation 4/26/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 4/26/2022 Partial Approval CRAIG VAUGHAN
Shower Pan 4/26/2022 Approved CRAIG VAUGHAN
Drywall Nailing 5/5/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/5/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/1/2022 Corrections Issued CRAIG VAUGHAN
Final 8/1/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/1/2022 Approved CRAIG VAUGHAN
Gas Test 8/1/2022 Approved CRAIG VAUGHAN
Green Building Final 8/1/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 8/1/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 8/1/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 8/5/2022 Approved CRAIG VAUGHAN
Final 8/5/2022 OK to Issue CofO CRAIG VAUGHAN