4831 N ATOLL AVE 91423
Certificate Information: 4831 N ATOLL AVE 91423
- Application / Permit
- 21014-10000-02577
- Plan Check / Job No.
- B21LA09734
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT EXISTING DETACHED GARAGE INTO AN ADU PER ORDINANCE. SCOPE WILL ALSO INLCUDE A ADDITION.
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/17/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/23/2021 | WING SUEN |
| Plan Check Approved | 3/2/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 3/2/2022 | DANIEL ABRAMYAN |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 6/18/2024 | JACK KARGODORIAN |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
| CofO Issued | 7/23/2024 | RUBEN SALAS |
| Permit Finaled | 7/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/9/2021 | CARLOS AGUILERA |
| Construction within easement | Cleared | 10/4/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Contreras Roberto Carlos; Lic. No.: 1072413-B | , |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/29/2023 | Partial Approval | KIRK SANDERS |
| Footing/Foundation/Slab | 10/5/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 11/14/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 11/14/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 11/14/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 12/5/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 12/18/2023 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 1/22/2024 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 1/22/2024 | Approved | JOSE AVILA |
| Green Building Rough | 1/22/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/22/2024 | Approved | JOSE AVILA |
| MERV13>=Rough | 1/22/2024 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 1/22/2024 | Approved | JOSE AVILA |
| Shower Pan | 1/22/2024 | Approved | JOSE AVILA |
| Insulation | 1/30/2024 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 2/6/2024 | Approved | JOSE AVILA |
| Sewer | 4/1/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Sewer | 4/4/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 4/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 4/24/2024 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 4/24/2024 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 5/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 5/31/2024 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 5/31/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 5/31/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/5/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 6/5/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 6/5/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 6/10/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 6/10/2024 | Approved | SALVADOR MARTINEZ |
| Final | 6/17/2024 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 6/17/2024 | Approved | JACK KARGODORIAN |