4833 N ATOLL AVE 91423
Certificate Information: 4833 N ATOLL AVE 91423
- Application / Permit
- 21014-10000-02576
- Plan Check / Job No.
- B21LA09732
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. PROPOSED GROUND FLOOR ADDITION TO THE REAR OF (E) SFD TO EXTEND EXISTING KITCHEN.
- Permit Issued
- Issued on 2/2/2022
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | MICHAEL LOPEZ |
| Corrections Issued | 6/17/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 6/23/2021 | WING SUEN |
| Plan Check Approved | 8/6/2021 | MICHAEL LOPEZ |
| Issued | 2/2/2022 | APPLICANT |
| CofO in Progress | 12/23/2022 | JOHN COLEMAN |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/6/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Contreras Roberto Carlos; Lic. No.: 1072413-B | 10710 ANZAC AVENUE LOS ANGELES, CA 90059 |
| Engineer | Mevises,, Chainart; Lic. No.: S2664 | 20217 ELKWOOD ST CANOGA PARK, CA 913062313 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/2/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 3/7/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/10/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 3/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 3/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 3/24/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | RAFAEL CORTES |
| Insulation | 6/17/2022 | Partial Approval | RAFAEL CORTES |
| Deputy Wood Construction | 6/27/2022 | Conditional Approval | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/1/2022 | Partial Inspection | RAFAEL CORTES |
| MERV13>=Rough | 7/1/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 7/12/2022 | Corrections Issued | RAFAEL CORTES |
| Shower Pan | 7/12/2022 | Corrections Issued | RAFAEL CORTES |
| HVAC-Rough | 7/18/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 7/18/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 7/18/2022 | Approved | RAFAEL CORTES |
| Shower Pan | 7/18/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| MERV13>=Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/27/2022 | Approved | RAFAEL CORTES |
| Insulation | 8/2/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 8/10/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 8/10/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/28/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Final | 11/3/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 11/22/2022 | Partial Inspection | JOHN COLEMAN |
| HVAC-Final | 11/22/2022 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | JOHN COLEMAN |
| Smoke Detectors | 11/22/2022 | Approved | JOHN COLEMAN |
| Final | 12/23/2022 | OK to Issue CofO | JOHN COLEMAN |
| MERV13>=Final | 12/23/2022 | Approved | JOHN COLEMAN |