6333 W 81ST ST 90045

Certificate Information: 6333 W 81ST ST 90045

Application / Permit
21014-10000-02568
Plan Check / Job No.
B21LA09707
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition and remodelling of (E) SFD.
Permit Issued
Issued on 11/6/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SAMUEL GONZALEZ
Corrections Issued 6/4/2021 SAMUEL GONZALEZ
Plan Check Approved 10/18/2021 RAMA DABADGE
Issued 11/6/2021 APPLICANT
Building Plans Picked Up 12/21/2021 APPLICANT
CofO in Progress 10/5/2022 HERBERT GIRON
Permit Finaled 10/6/2022 DANIEL ORRANTE
CofO Issued 10/6/2022 DANIEL ORRANTE
Permit Finaled 10/6/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 6/10/2021 HISASHI KOBAYAKAWA
Low Impact Development Cleared 9/29/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/4/2021 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/2/2021 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 12/13/2021 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 12/22/2021 No Access for Inspection ENRIQUE MIRELES
Pre-Inspection 12/23/2021 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 1/7/2022 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 1/11/2022 Approved DAVID FEILER
Underground Mechanical 1/21/2022 Corrections Issued DAVID FEILER
Underground Mechanical 1/26/2022 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 1/28/2022 Corrections Issued RYAN SALAZAR
PLUMBING-Rough 2/1/2022 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 3/18/2022 Partial Approval JESUS RODRIGUEZ
Green Building Rough 3/18/2022 Not Ready for Inspection JESUS RODRIGUEZ
Wood Frame 3/18/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 3/23/2022 Corrections Issued JESUS RODRIGUEZ
Wood Frame 3/23/2022 Partial Approval JESUS RODRIGUEZ
HVAC-Rough 3/25/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 3/25/2022 Partial Approval JESUS RODRIGUEZ
Green Building Rough 4/1/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/1/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 4/11/2022 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 4/11/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/11/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/13/2022 Approved JESUS RODRIGUEZ
Insulation 4/13/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 4/26/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 4/26/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/26/2022 Approved JESUS RODRIGUEZ
Shower Pan 4/26/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/1/2022 Not Ready for Inspection HERBERT GIRON
Final 9/1/2022 Corrections Issued HERBERT GIRON
Green Building Final 9/1/2022 Corrections Issued HERBERT GIRON
HVAC-Final 9/1/2022 Not Ready for Inspection HERBERT GIRON
PLUMBING-Final 9/1/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved HERBERT GIRON
Smoke Detectors 9/1/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/7/2022 Corrections Issued BOBBY KEY
Final 9/7/2022 Not Ready for Inspection BOBBY KEY
Gas Test 9/7/2022 Not Ready for Inspection BOBBY KEY
Green Building Final 9/7/2022 Corrections Issued BOBBY KEY
HVAC-Final 9/7/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 9/7/2022 Conditional Approval BOBBY KEY
Smoke Detectors 9/7/2022 Approved BOBBY KEY
HVAC-Final 9/20/2022 Partial Approval BOBBY KEY
ELECTRICAL-Final 9/21/2022 Corrections Issued HERBERT GIRON
Final 9/21/2022 Corrections Issued HERBERT GIRON
Gas Test 9/21/2022 Corrections Issued HERBERT GIRON
Green Building Final 9/21/2022 Approved HERBERT GIRON
HVAC-Final 9/21/2022 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 9/27/2022 Approved HERBERT GIRON
Final 9/27/2022 Corrections Issued HERBERT GIRON
Gas Test 9/27/2022 Corrections Issued HERBERT GIRON
HVAC-Final 9/27/2022 Approved HERBERT GIRON
PLUMBING-Final 9/27/2022 Corrections Issued HERBERT GIRON
Final 9/29/2022 Corrections Issued HERBERT GIRON
Gas Test 9/29/2022 Corrections Issued HERBERT GIRON
PLUMBING-Final 9/29/2022 Corrections Issued HERBERT GIRON
Final 10/5/2022 OK to Issue CofO HERBERT GIRON
Gas Test 10/5/2022 Approved HERBERT GIRON
PLUMBING-Final 10/5/2022 Approved HERBERT GIRON