6333 W 81ST ST 90045
Certificate Information: 6333 W 81ST ST 90045
- Application / Permit
- 21014-10000-02568
- Plan Check / Job No.
- B21LA09707
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- One story addition and remodelling of (E) SFD.
- Permit Issued
- Issued on 11/6/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 6/4/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/18/2021 | RAMA DABADGE |
| Issued | 11/6/2021 | APPLICANT |
| Building Plans Picked Up | 12/21/2021 | APPLICANT |
| CofO in Progress | 10/5/2022 | HERBERT GIRON |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 6/10/2021 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 9/29/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/4/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2021 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 12/13/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 12/22/2021 | No Access for Inspection | ENRIQUE MIRELES |
| Pre-Inspection | 12/23/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/7/2022 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 1/11/2022 | Approved | DAVID FEILER |
| Underground Mechanical | 1/21/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 1/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/28/2022 | Corrections Issued | RYAN SALAZAR |
| PLUMBING-Rough | 2/1/2022 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 3/18/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Wood Frame | 3/18/2022 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/23/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 3/23/2022 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 3/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/25/2022 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Rough | 4/1/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/1/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/11/2022 | Conditional Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 4/11/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 4/11/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 4/13/2022 | Approved | JESUS RODRIGUEZ |
| Insulation | 4/13/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 4/26/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/26/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 4/26/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/26/2022 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| Final | 9/1/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 9/1/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 9/1/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 9/1/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 9/1/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | BOBBY KEY |
| Final | 9/7/2022 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 9/7/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 9/7/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 9/7/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/7/2022 | Conditional Approval | BOBBY KEY |
| Smoke Detectors | 9/7/2022 | Approved | BOBBY KEY |
| HVAC-Final | 9/20/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Final | 9/21/2022 | Corrections Issued | HERBERT GIRON |
| Final | 9/21/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 9/21/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 9/21/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 9/21/2022 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 9/27/2022 | Approved | HERBERT GIRON |
| Final | 9/27/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 9/27/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 9/27/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 9/27/2022 | Corrections Issued | HERBERT GIRON |
| Final | 9/29/2022 | Corrections Issued | HERBERT GIRON |
| Gas Test | 9/29/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 9/29/2022 | Corrections Issued | HERBERT GIRON |
| Final | 10/5/2022 | OK to Issue CofO | HERBERT GIRON |
| Gas Test | 10/5/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/5/2022 | Approved | HERBERT GIRON |