14115 S MENLO AVE 90247

Certificate Information: 14115 S MENLO AVE 90247

Application / Permit
21014-10000-02558
Plan Check / Job No.
B21LA09670
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) GARAGE TO ADU AND SECOND FLOOR ADDITION (336 SF). 2 OF 2
Permit Issued
Issued on 12/22/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 VIVIAN LAO
Corrections Issued 7/8/2021 VIVIAN LAO
Quality Review Completed 7/19/2021 MICHAEL PEREZ
Building Plans Picked Up 7/21/2021 APPLICANT
Applicant returned to address corrections 5/10/2022 VIVIAN LAO
Plan Check Approved 5/24/2022 VIVIAN LAO
Issued 12/22/2022 APPLICANT
CofO in Progress 8/28/2025 BEN MOLSTAD
Permit Finaled 8/29/2025 ANSON MAGLASANG
CofO Issued 8/29/2025 ANSON MAGLASANG
Permit Finaled 8/29/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/8/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/13/2021 JOSE HERNANDEZ
Sewer availability Cleared 10/13/2021 JOSE HERNANDEZ
Hydrant and Access approval Cleared 1/7/2022 GILBERT URREA
Low Impact Development Cleared 2/4/2022 NICK RAYGOZA
Construction within easement Cleared 4/8/2022 RIDWAN HARDY
Roof/Waste drainage to street Cleared 4/25/2022 ERIK BEASLEY

Contact Information

Architect Gaetos,, Benjamin Abat; Lic. No.: C31227 5129 CASPAR AVENUE      LOS ANGELES, CA 90041
Contractor Ruiz'S Construction & Landscaping; Lic. No.: 903602-B 274 E ROWLAND ST      COVINA, CA 91723
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2023 Approved JOHN KLARIN
METHANE-Barrier 1/26/2023 Approved JOHN KLARIN
METHANE-Subgrade 1/26/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/6/2023 Approved JAMES CHAVEZ
Wood Frame 2/6/2023 Partial Inspection JAMES CHAVEZ
ELECTRICAL-Rough 3/7/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 3/7/2023 Approved JAMES CHAVEZ
Wood Frame 3/7/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 3/14/2023 Approved EUGENE CASSIDY
PLUMBING-Rough 3/14/2023 Approved EUGENE CASSIDY
Special/Order Compliance 3/14/2023 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 3/16/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 3/23/2023 Approved JAMES CHAVEZ
Insulation 4/4/2023 Approved JAMES CHAVEZ
Drywall Nailing 4/27/2023 Approved JAMES CHAVEZ
Green Building Rough 4/27/2023 Approved JAMES CHAVEZ
Service/Power Release 6/27/2024 Corrections Issued JAMES CHAVEZ
Special/Order Compliance 7/9/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 7/25/2024 Approved JAMES CHAVEZ
Final 7/25/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 7/25/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Final 7/25/2024 Approved JAMES CHAVEZ
MERV13>=Rough 7/25/2024 Approved JAMES CHAVEZ
METHANE-Final 7/25/2024 Approved JAMES CHAVEZ
METHANE-Rough 7/25/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 7/25/2024 Approved JAMES CHAVEZ
ELECTRICAL-Final 8/23/2024 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 10/8/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 10/11/2024 Corrections Issued BEN MOLSTAD
Final 10/11/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 10/16/2024 Approved BEN MOLSTAD
Final 10/16/2024 Corrections Issued BEN MOLSTAD
Final 12/13/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 12/13/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/13/2024 SGSOV Approved EUGENE CASSIDY
Final 1/31/2025 Not Ready for Inspection BEN MOLSTAD
Final 2/7/2025 Not Ready for Inspection BEN MOLSTAD
Final 6/20/2025 Not Ready for Inspection BEN MOLSTAD
Final 8/26/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 8/28/2025 Approved BEN MOLSTAD
Final 8/28/2025 OK to Issue CofO BEN MOLSTAD
HVAC-Final 8/28/2025 Approved BEN MOLSTAD
PLUMBING-Final 8/28/2025 Approved BEN MOLSTAD