6071 E ROY ST 90042

Certificate Information: 6071 E ROY ST 90042

Application / Permit
21014-10000-02556
Plan Check / Job No.
B21LA09668
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2ND STORY ADDITION, INTERIOR AND EXTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 11/12/2021
Issuing Office
Current Status
CofO Issued on 1/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 DANIEL YIP
Corrections Issued 6/14/2021 DANIEL YIP
Quality Review Completed 6/22/2021 JASON HEALEY
Applicant returned to address corrections 10/18/2021 DANIEL YIP
Applicant returned to address corrections 11/1/2021 DANIEL YIP
Plan Check Approved 11/3/2021 DANIEL YIP
Issued 11/12/2021 APPLICANT
Building Plans Picked Up 11/24/2021 APPLICANT
CofO in Progress 1/25/2023 CRAIG VAUGHAN
Permit Finaled 1/27/2023 DEROLD HAUFF
CofO Issued 1/27/2023 DEROLD HAUFF
Permit Finaled 1/27/2023 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/7/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/7/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/7/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/7/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 7/7/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 7/7/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 7/12/2021 STEVE MELGAR
Sewer availability Cleared 7/12/2021 STEVE MELGAR
Low Impact Development Cleared 9/16/2021 SAHIL SHARMA
Excavation more than 5-ft deep Cleared 10/18/2021 CALOSHA APPROVED
GPI Written Notices Cleared 10/18/2021 DANIEL YIP
Grading Pre-Inspection Cleared 10/18/2021 DANIEL YIP

Contact Information

Contractor Delta Remodeling Inc; Lic. No.: 913496-B 8309 TUJUNGA AVENUE #105      SUN VALLEY, CA 91352
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/20/2021 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 12/21/2021 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/21/2021 Corrections Issued LILIANA PORTILLO
Excavation/Setback/Form/Re-Bar 1/4/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 1/4/2022 Approved CRAIG VAUGHAN
Wood Frame 2/8/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 7/5/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 7/5/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/19/2022 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 7/19/2022 Approved CRAIG VAUGHAN
Shower Pan 7/19/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 7/22/2022 Approved CRAIG VAUGHAN
Drywall Nailing 8/11/2022 Approved KATHRYN BUTTERWORTH
Insulation 8/11/2022 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 10/19/2022 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 1/20/2023 Corrections Issued CRAIG VAUGHAN
Final 1/20/2023 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 1/20/2023 Approved CRAIG VAUGHAN
HVAC-Final 1/20/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 1/20/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/20/2023 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 1/20/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Final 1/24/2023 Approved CRAIG VAUGHAN
Final 1/24/2023 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 1/24/2023 Approved CRAIG VAUGHAN
PLUMBING-Final 1/24/2023 Approved CRAIG VAUGHAN