1348 W 221ST ST 90501

Certificate Information: 1348 W 221ST ST 90501

Application / Permit
21014-10000-02552
Plan Check / Job No.
B21LA09648
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2ND STORY ADDITION, INTERIOR AND EXTERIOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 12/4/2021
Issuing Office
Current Status
CofO Issued on 7/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 DANIEL YIP
Corrections Issued 6/14/2021 DANIEL YIP
Quality Review Completed 6/18/2021 JASON HEALEY
Applicant returned to address corrections 8/25/2021 DANIEL YIP
Plan Check Approved 11/24/2021 DANIEL YIP
Issued 12/4/2021 APPLICANT
Building Plans Picked Up 12/22/2021 APPLICANT
CofO in Progress 6/29/2022 DONALD CRICHLOW
Permit Finaled 7/19/2022 DEROLD HAUFF
CofO Issued 7/19/2022 DEROLD HAUFF
Permit Finaled 7/19/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/27/2021 ERIK BEASLEY
Sewer availability Cleared 7/27/2021 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/28/2021 ERIK BEASLEY

Contact Information

Contractor 3000 Construction; Lic. No.: 994421-B 11955 MANOR DR APT 1      HAWTHORNE, CA 90250
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240
Engineer Wang,, Kenneth Kaiyen; Lic. No.: C25386 147 PALATINE DR      ALHAMBRA, CA 91801
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/8/2021 Partial Approval JOHN KLARIN
Excavation/Setback/Form/Re-Bar 12/20/2021 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 12/20/2021 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 1/18/2022 Partial Approval ANSON MAGLASANG
BUILDING-Rough-Frame 2/11/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 2/11/2022 Partial Approval EUGENE CASSIDY
Green Building Rough 2/11/2022 Approved EUGENE CASSIDY
HVAC-Rough 2/11/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 2/11/2022 Approved EUGENE CASSIDY
Shower Pan 2/11/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 2/17/2022 Conditional Approval EUGENE CASSIDY
Insulation 2/17/2022 Approved EUGENE CASSIDY
Shower Pan 2/17/2022 Approved EUGENE CASSIDY
Drywall Nailing 2/24/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/24/2022 Partial Approval EUGENE CASSIDY
Interior/Exterior Lathing 3/2/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 3/22/2022 Corrections Issued EUGENE CASSIDY
HVAC-Final 3/22/2022 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 4/8/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 4/8/2022 Not Ready for Inspection EUGENE CASSIDY
Final 4/8/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 4/8/2022 Approved EUGENE CASSIDY
Green Building Final 4/8/2022 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 4/8/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/8/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 4/8/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/13/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 6/13/2022 Approved EUGENE CASSIDY
Final 6/13/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 6/13/2022 Approved EUGENE CASSIDY
HVAC-Final 6/13/2022 Approved EUGENE CASSIDY
PLUMBING-Final 6/13/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Approved EUGENE CASSIDY
Final 6/22/2022 Not Ready for Inspection EUGENE CASSIDY
Final 6/28/2022 OK to Issue CofO EUGENE CASSIDY