5950-5952 N FAIR AVE 91606
Certificate Information: 5950-5952 N FAIR AVE 91606
- Application / Permit
- 21014-10000-02537
- Plan Check / Job No.
- B21LA09582
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH NEW ADDITION INTO TWO ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- CofO Issued on 6/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | KEVIN MORALES |
| Corrections Issued | 7/9/2021 | KEVIN MORALES |
| Quality Review Completed | 7/13/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 7/21/2021 | APPLICANT |
| Plan Check Approved | 8/11/2021 | KEVIN MORALES |
| Issued | 8/19/2021 | APPLICANT |
| CofO in Progress | 5/28/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
| CofO Issued | 6/18/2025 | RUBEN SALAS |
| Permit Finaled | 6/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/22/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 7/28/2021 | WALTER RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/29/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/6/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 3/6/2024 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 3/8/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 3/8/2024 | Partial Approval | JOHN HAYES |
| Deputy Drilled-In Anchors | 3/13/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Approved | JOHN COLEMAN |
| Footing/Foundation/Slab | 3/21/2024 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/31/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/31/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/31/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 6/11/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/11/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/17/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 7/9/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/9/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 11/22/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 2/4/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/4/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 2/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 3/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 5/27/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 5/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |