1860 W 69TH ST 90047

Certificate Information: 1860 W 69TH ST 90047

Application / Permit
21014-10000-02534
Plan Check / Job No.
B21LA09581
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDTION TO AND CONVERSION OF ARAGE INTO ADU
Permit Issued
Issued on 9/18/2021
Issuing Office
Current Status
Issued on 9/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 5/21/2021 SINA KHOSRAVI
Corrections Issued 5/22/2021 SINA KHOSRAVI
Applicant returned to address corrections 7/8/2021 JESSE JIMENEZ
Applicant returned to address corrections 8/13/2021 RAHEL BEYENE
Plan Check Approved 9/2/2021 JOSEPH RAFOLS
Issued 9/18/2021 APPLICANT
Building Plans Picked Up 9/21/2021 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/21/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 6/21/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 6/23/2021 WALLIE JONG
Sewer availability Cleared 6/23/2021 WALLIE JONG
Permit Cleared 8/4/2021 WALLIE JONG
Construction near power lines Cleared 9/2/2021 JOHN BACON

Contact Information

Contractor Daniels 3a2c Construction Inc; Lic. No.: 1052545-B 1245 S LABREA #124      INGLEWOOD, CA 90301

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/8/2021 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/20/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/29/2021 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 11/29/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 11/29/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 12/2/2021 Approved FREDDIE RIVERA
Green Building Rough 12/2/2021 Approved FREDDIE RIVERA
HVAC-Rough 12/2/2021 Approved FREDDIE RIVERA
Insulation 12/10/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/10/2021 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 12/15/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 12/20/2021 Approved LILIANA PORTILLO
Final 4/12/2022 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/12/2022 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/12/2022 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 4/12/2022 Approved ENRIQUE MIRELES
Final 6/17/2022 Corrections Issued SHAVONNE ESPINOZA
Final 6/23/2022 Corrections Issued HORACE FULTZ
ELECTRICAL-Final 11/14/2022 Approved ENRIQUE MIRELES
Final 11/14/2022 Corrections Issued ENRIQUE MIRELES
HVAC-Final 11/14/2022 Approved ENRIQUE MIRELES
PLUMBING-Final 11/14/2022 Approved ENRIQUE MIRELES
Service/Power Release 11/14/2022 Approved ENRIQUE MIRELES