867 S MUIRFIELD ROAD 90005

Certificate Information: 867 S MUIRFIELD ROAD 90005

Application / Permit
21014-10000-02516
Plan Check / Job No.
B21LA09494
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ALTERATION AND ADDITION TO 2-STORY SFD, including rooftop deck.
Permit Issued
Issued on 7/8/2022
Issuing Office
Metro
Current Status
Issued on 7/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 6/2/2021 SINA KHOSRAVI
Corrections Issued 6/3/2021 SINA KHOSRAVI
Applicant returned to address corrections 9/29/2021 SINA KHOSRAVI
Applicant returned to address corrections 11/28/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 1/30/2022 AUNG SOE
Plan Check Approved 4/19/2022 ADAM HEGAZI
Building Plans Picked Up 4/29/2022 APPLICANT
Issued 7/8/2022 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/21/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 6/28/2021 WALLIE JONG
Sewer availability Cleared 6/28/2021 WALLIE JONG

Contact Information

Architect Bernstein,, M Charles; Lic. No.: C10668 20575 CHENEY DRIVE      TOPANGA, CA 90290
Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/23/2022 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 9/1/2022 Approved JEFFREY MEAD
METHANE-Barrier 9/1/2022 Approved JEFFREY MEAD
METHANE-Subgrade 9/1/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 11/28/2022 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 11/28/2022 Corrections Issued JEFFREY MEAD
Green Building Rough 11/28/2022 Not Ready for Inspection JEFFREY MEAD
METHANE-Rough 11/28/2022 Approved JEFFREY MEAD
PLUMBING-Rough 11/28/2022 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 12/12/2022 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 12/16/2022 No Access for Inspection MICHAEL LEWIS
PLUMBING-Rough 12/21/2022 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 12/28/2022 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 1/3/2023 Approved JEFFREY MEAD
HVAC-Rough 1/3/2023 Not Ready for Inspection JEFFREY MEAD
Wood Frame 1/3/2023 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 1/10/2023 Corrections Issued JEFFREY MEAD
Green Building Rough 1/10/2023 Not Ready for Inspection JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 1/31/2023 Partial Approval JEFFREY MEAD
HVAC-Rough 1/31/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 1/31/2023 Approved JEFFREY MEAD
Gas Test 2/7/2023 Not Ready for Inspection JEFFREY MEAD
HVAC-Rough 2/7/2023 Partial Approval JEFFREY MEAD
Gas Test 2/13/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 2/13/2023 Approved CRAIG VAUGHAN
Wood Frame 2/13/2023 Corrections Issued CRAIG VAUGHAN
Wood Frame 2/16/2023 Partial Inspection MICHAEL LEWIS
BUILDING-Rough-Frame 2/27/2023 Partial Approval JEFFREY MEAD
Green Building Rough 2/27/2023 Not Ready for Inspection JEFFREY MEAD
Pre-Inspection 2/27/2023 Approved JEFFREY MEAD
Wood Frame 2/27/2023 Partial Approval JEFFREY MEAD
Interior/Exterior Lathing 4/13/2023 Approved MICHAEL LEWIS
Insulation 4/26/2023 Approved JEFFREY MEAD
Shower Pan 4/26/2023 Approved JEFFREY MEAD
Drywall Nailing 5/11/2023 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 8/20/2024 Partial Approval JEFFREY MEAD
PLUMBING-Rough 9/17/2024 No Access for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 9/10/2025 Not Ready for Inspection JEFFREY MEAD
Final 9/10/2025 Corrections Issued JEFFREY MEAD
Green Building Final 9/10/2025 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 9/10/2025 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 9/10/2025 Not Ready for Inspection JEFFREY MEAD