2132 W COVE AVE 90039
Certificate Information: 2132 W COVE AVE 90039
- Application / Permit
- 21014-10000-02507
- Plan Check / Job No.
- B21LA09455
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ATTACHED PATIO COVER TO (E) SFD
- Permit Issued
- Issued on 4/19/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2021 | FERNANDO FLORES |
| Corrections Issued | 7/15/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/28/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 2/15/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 3/9/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 3/31/2022 | RICARDO RAMIREZ |
| Issued | 4/19/2022 | APPLICANT |
| Building Plans Picked Up | 4/21/2022 | APPLICANT |
| CofO in Progress | 12/1/2022 | THOMAS LOGRASSO |
| CofO Issued | 12/5/2022 | DEROLD HAUFF |
| Permit Finaled | 12/5/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/10/2022 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | TREVOR QUAN |
| Tenant Habitability Plan | Cleared | 2/28/2022 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ehsan,, Bahman; Lic. No.: S1708 | 3440 OAKMONT VIEW DR GLENDALE, CA 91208 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/1/2022 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/29/2022 | Conditional Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/28/2022 | Approved | THOMAS LOGRASSO |
| Final | 10/28/2022 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 10/28/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 12/1/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 12/1/2022 | Approved | THOMAS LOGRASSO |