1958 N JONES AVE 90032
Certificate Information: 1958 N JONES AVE 90032
- Application / Permit
- 21014-10000-02457
- Plan Check / Job No.
- B21LA09291
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- supplemental to 20016-10000-02316 to add new 162 sf to a previously approed 363sf garage to ADU conversion per engineer design. Addition inlcudes a bedroom with closet.
- Permit Issued
- Issued on 12/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 6/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 6/7/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/5/2021 | AUNG SOE |
| Applicant returned to address corrections | 10/12/2021 | ZAW HAN |
| Plan Check Approved | 10/14/2021 | ZAW HAN |
| Issued | 12/3/2021 | APPLICANT |
| Building Plans Picked Up | 12/8/2021 | APPLICANT |
| Permit Finaled | 6/21/2023 | RUBEN SALAS |
| CofO in Progress | 6/21/2023 | AMY COLIN |
| No Progress | 6/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/8/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 9/21/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 9/27/2021 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 10/13/2021 | CELINA MORENO |
Contact Information
| Contractor | Iconx Inc; Lic. No.: 980801-B | 4248 PANAMINT STREET LOS ANGELES, CA 90065 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/13/2021 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 1/18/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 4/14/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Approved | AMY COLIN |
| HVAC-Rough | 4/14/2022 | Approved | AMY COLIN |
| Wood Frame | 4/14/2022 | Approved | AMY COLIN |
| Insulation | 4/20/2022 | Approved | ADAM ESCOTO |
| Interior/Exterior Lathing | 4/20/2022 | Partial Approval | ADAM ESCOTO |
| Insulation | 4/22/2022 | Corrections Issued | RUBEN SALAS |
| Drywall Nailing | 5/3/2022 | Approved | AMY COLIN |
| Green Building Rough | 5/3/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | AMY COLIN |
| Final | 12/29/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 12/29/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 12/29/2022 | Approved | AMY COLIN |
| Final | 6/21/2023 | OK to Issue CofO | AMY COLIN |