2045 W BROWNING BLVD 90062

Certificate Information: 2045 W BROWNING BLVD 90062

Application / Permit
21014-10000-02432
Plan Check / Job No.
B21LA09225
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ONE STORY 25'-10" X 16'-5"ADDITION FOR ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/17/2021 JESSE JIMENEZ
Corrections Issued 5/18/2021 JESSE JIMENEZ
Plan Check Approved 11/2/2021 GEORGE ALVAREZ
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/14/2022 APPLICANT
CofO in Progress 4/30/2024 SABAS ALONSO
Permit Finaled 5/1/2024 DEROLD HAUFF
CofO Issued 5/1/2024 DEROLD HAUFF
Permit Finaled 5/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/21/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 6/21/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 6/23/2021 RENZ SORIANO
Community Plan Implem. Overlay Cleared 8/3/2021 RIDWAN HARDY
Construction near power lines Cleared 8/3/2021 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 9/13/2021 RAFAEL FONTES
Sewer availability Cleared 9/15/2021 RENZ SORIANO
Hydrant and Access approval Cleared 10/2/2021 ROBERT DUFF
Tenant Habitability Plan Cleared 10/12/2021 RICHARD BRINSON

Contact Information

Contractor C G S Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/7/2022 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 12/7/2022 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 12/15/2022 Approved HORACE FULTZ
Footing/Foundation/Slab 12/15/2022 Approved HORACE FULTZ
Deputy Drilled-In Anchors 12/16/2022 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/19/2023 Approved SABAS ALONSO
Green Building Rough 2/21/2023 Approved SABAS ALONSO
HVAC-Rough 2/21/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 2/21/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 2/21/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 3/3/2023 Approved SABAS ALONSO
Insulation 3/3/2023 Approved SABAS ALONSO
Gas Test 4/14/2023 Not Ready for Inspection SABAS ALONSO
Sewer 4/14/2023 Approved SABAS ALONSO
Underground Mechanical 4/14/2023 Approved SABAS ALONSO
Gas Test 4/17/2023 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 4/17/2023 Not Ready for Inspection SABAS ALONSO
Sewer 4/17/2023 Approved SABAS ALONSO
Drywall Nailing 6/26/2023 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 9/20/2023 Approved LILIANA PORTILLO
Final 2/15/2024 Corrections Issued SABAS ALONSO
Green Building Final 2/15/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/15/2024 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 2/15/2024 Approved SABAS ALONSO
Final 3/4/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 3/4/2024 SGSOV Approved SABAS ALONSO
Final 4/8/2024 Corrections Issued SABAS ALONSO
Final 4/29/2024 OK to Issue CofO SABAS ALONSO