2045 W BROWNING BLVD 90062
Certificate Information: 2045 W BROWNING BLVD 90062
- Application / Permit
- 21014-10000-02432
- Plan Check / Job No.
- B21LA09225
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ONE STORY 25'-10" X 16'-5"ADDITION FOR ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 5/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2021 | JESSE JIMENEZ |
| Corrections Issued | 5/18/2021 | JESSE JIMENEZ |
| Plan Check Approved | 11/2/2021 | GEORGE ALVAREZ |
| Issued | 1/12/2022 | APPLICANT |
| Building Plans Picked Up | 1/14/2022 | APPLICANT |
| CofO in Progress | 4/30/2024 | SABAS ALONSO |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
| CofO Issued | 5/1/2024 | DEROLD HAUFF |
| Permit Finaled | 5/1/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 6/21/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2021 | RENZ SORIANO |
| Community Plan Implem. Overlay | Cleared | 8/3/2021 | RIDWAN HARDY |
| Construction near power lines | Cleared | 8/3/2021 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 9/13/2021 | RAFAEL FONTES |
| Sewer availability | Cleared | 9/15/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 10/2/2021 | ROBERT DUFF |
| Tenant Habitability Plan | Cleared | 10/12/2021 | RICHARD BRINSON |
Contact Information
| Contractor | C G S Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 12/7/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Approved | HORACE FULTZ |
| Footing/Foundation/Slab | 12/15/2022 | Approved | HORACE FULTZ |
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/21/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/21/2023 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 2/21/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | SABAS ALONSO |
| Insulation | 3/3/2023 | Approved | SABAS ALONSO |
| Gas Test | 4/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 4/14/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/14/2023 | Approved | SABAS ALONSO |
| Gas Test | 4/17/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 4/17/2023 | Not Ready for Inspection | SABAS ALONSO |
| Sewer | 4/17/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/26/2023 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/20/2023 | Approved | LILIANA PORTILLO |
| Final | 2/15/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 2/15/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 2/15/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 2/15/2024 | Approved | SABAS ALONSO |
| Final | 3/4/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | SABAS ALONSO |
| Final | 4/8/2024 | Corrections Issued | SABAS ALONSO |
| Final | 4/29/2024 | OK to Issue CofO | SABAS ALONSO |