14144 W HORTENSE ST 91423

Certificate Information: 14144 W HORTENSE ST 91423

Application / Permit
21014-10000-02419
Plan Check / Job No.
B21LA09185
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY ADU (448 SF) WITH 2-CAR GARAGE ON FIRST FLOOR PER LAMC 12.22A33(c)-(d). 2 OF 2
Permit Issued
Issued on 1/6/2022
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 VIVIAN LAO
Corrections Issued 6/30/2021 VIVIAN LAO
Quality Review Completed 7/8/2021 MICHAEL PEREZ
Applicant returned to address corrections 8/19/2021 VIVIAN LAO
Applicant returned to address corrections 8/23/2021 VIVIAN LAO
Applicant returned to address corrections 9/22/2021 VIVIAN LAO
Applicant returned to address corrections 10/14/2021 VIVIAN LAO
Applicant returned to address corrections 12/23/2021 VIVIAN LAO
Plan Check Approved 12/29/2021 VIVIAN LAO
Issued 1/6/2022 APPLICANT
Building Plans Picked Up 1/7/2022 APPLICANT
CofO in Progress 2/10/2025 MISAEL ESPARZA
Permit Finaled 3/6/2025 RUBEN SALAS
CofO Issued 3/6/2025 RUBEN SALAS
Permit Finaled 3/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/2/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 8/2/2021 GABRIEL ROBLES
Sewer availability Cleared 8/2/2021 GABRIEL ROBLES
ZI Cleared 10/19/2021 MAXFIELD VERMY
Low Impact Development Cleared 12/6/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 12/10/2021 CARLOS AGUILERA

Contact Information

Architect Volbeda,, Pete; Lic. No.: C13077 P.O. BOX 1665      UPLAND, CA 91785
Contractor Walcon Building & Construction Inc; Lic. No.: 1073699-B 801 S GRAND AVE UNIT 1202      LOS ANGELES, CA 90017

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/12/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/12/2022 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/22/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 4/22/2022 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 4/26/2022 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/27/2022 Approved MISAEL ESPARZA
Footing/Foundation/Slab 4/27/2022 Approved MISAEL ESPARZA
PLUMBING-Rough 4/27/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/1/2022 Not Ready for Inspection RAUL OLAGI
Verify Sprinkler Sign Off 8/1/2022 Not Ready for Inspection RAUL OLAGI
Wood Frame 8/1/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 8/9/2022 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 8/9/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Approved MATTHEW NELSON
Wood Frame 9/19/2022 Partial Approval MATTHEW NELSON
Deputy Wood Construction 4/27/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/9/2023 Corrections Issued JOHN COLEMAN
Green Building Rough 6/9/2023 Not Ready for Inspection JOHN COLEMAN
MERV13>=Rough 6/9/2023 Approved JOHN COLEMAN
Rough-Elec/Plmb/HVAC 6/9/2023 No Access for Inspection JOHN COLEMAN
Verify Sprinkler Sign Off 6/9/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 6/16/2023 No Access for Inspection JOHN COLEMAN
PLUMBING-Rough 6/16/2023 No Access for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 8/24/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 8/24/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/24/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 8/24/2023 Corrections Issued MISAEL ESPARZA
Verify Sprinkler Sign Off 8/24/2023 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 11/9/2023 Approved MISAEL ESPARZA
ELECTRICAL-Rough 11/9/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/9/2023 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 11/9/2023 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 11/9/2023 Approved MISAEL ESPARZA
Insulation 1/12/2024 Approved MISAEL ESPARZA
Service/Power Release 1/12/2024 Not Ready for Inspection MISAEL ESPARZA
Drywall Nailing 1/25/2024 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 1/25/2024 Partial Inspection MISAEL ESPARZA
Drywall Nailing 2/7/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/7/2024 Approved MISAEL ESPARZA
Shower Pan 2/7/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 5/9/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 5/9/2024 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 6/6/2024 Not Ready for Inspection JOHN COLEMAN
HVAC-Final 6/6/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Final 6/6/2024 Approved JOHN COLEMAN
Service/Power Release 6/6/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 1/3/2025 Approved JACK KARGODORIAN
HVAC-Final 1/3/2025 Approved JACK KARGODORIAN
PLUMBING-Final 1/3/2025 Approved JACK KARGODORIAN
Smoke Detectors 1/3/2025 Approved JACK KARGODORIAN
Final 2/7/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 2/7/2025 Approved MISAEL ESPARZA
MERV13>=Final 2/7/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 2/7/2025 Approved MISAEL ESPARZA