14144 W HORTENSE ST 91423
Certificate Information: 14144 W HORTENSE ST 91423
- Application / Permit
- 21014-10000-02419
- Plan Check / Job No.
- B21LA09185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ADU (448 SF) WITH 2-CAR GARAGE ON FIRST FLOOR PER LAMC 12.22A33(c)-(d). 2 OF 2
- Permit Issued
- Issued on 1/6/2022
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | VIVIAN LAO |
| Corrections Issued | 6/30/2021 | VIVIAN LAO |
| Quality Review Completed | 7/8/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/19/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 8/23/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 9/22/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 10/14/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 12/23/2021 | VIVIAN LAO |
| Plan Check Approved | 12/29/2021 | VIVIAN LAO |
| Issued | 1/6/2022 | APPLICANT |
| Building Plans Picked Up | 1/7/2022 | APPLICANT |
| CofO in Progress | 2/10/2025 | MISAEL ESPARZA |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
| CofO Issued | 3/6/2025 | RUBEN SALAS |
| Permit Finaled | 3/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/2/2021 | GABRIEL ROBLES |
| ZI | Cleared | 10/19/2021 | MAXFIELD VERMY |
| Low Impact Development | Cleared | 12/6/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CARLOS AGUILERA |
Contact Information
| Architect | Volbeda,, Pete; Lic. No.: C13077 | P.O. BOX 1665 UPLAND, CA 91785 |
| Contractor | Walcon Building & Construction Inc; Lic. No.: 1073699-B | 801 S GRAND AVE UNIT 1202 LOS ANGELES, CA 90017 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/12/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/22/2022 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/26/2022 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/27/2022 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/27/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/1/2022 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 8/1/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 8/1/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 8/9/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/9/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | MATTHEW NELSON |
| Wood Frame | 9/19/2022 | Partial Approval | MATTHEW NELSON |
| Deputy Wood Construction | 4/27/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/9/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| MERV13>=Rough | 6/9/2023 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 6/9/2023 | No Access for Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 6/9/2023 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/16/2023 | No Access for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 6/16/2023 | No Access for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 8/24/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 8/24/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/24/2023 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/24/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/9/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/9/2023 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 11/9/2023 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 11/9/2023 | Approved | MISAEL ESPARZA |
| Insulation | 1/12/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 1/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 1/25/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/25/2024 | Partial Inspection | MISAEL ESPARZA |
| Drywall Nailing | 2/7/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/7/2024 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/7/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/9/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/9/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 6/6/2024 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Final | 6/6/2024 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Final | 6/6/2024 | Approved | JOHN COLEMAN |
| Service/Power Release | 6/6/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 1/3/2025 | Approved | JACK KARGODORIAN |
| HVAC-Final | 1/3/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 1/3/2025 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 1/3/2025 | Approved | JACK KARGODORIAN |
| Final | 2/7/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 2/7/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 2/7/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 2/7/2025 | Approved | MISAEL ESPARZA |