3830 W CARNAVON WAY 90027
Certificate Information: 3830 W CARNAVON WAY 90027
- Application / Permit
- 21014-10000-02415
- Plan Check / Job No.
- B21LA09178
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- CONVERSION OF EXISTING SPACE AND NEW ADDITION TO EXISTING SFD FOR NEW ATTACHED REC. ROOM. INTERIOR AND EXTERIOR STR. REMODEL PER PROVIDED IN THE PLAN.
- Permit Issued
- Issued on 2/17/2023
- Issuing Office
- Current Status
- CofO Issued on 10/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/1/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/13/2021 | JASON HEALEY |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Applicant returned to address corrections | 1/12/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 11/15/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 1/3/2023 | MAHNAZ NOURHASHEMI |
| Issued | 2/17/2023 | APPLICANT |
| CofO in Progress | 9/23/2024 | ENRIQUE MIRELES |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
| CofO Issued | 10/2/2024 | RUBEN SALAS |
| Permit Finaled | 10/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | ABEL CASILLAS |
| Miscellaneous | Cleared | 10/24/2022 | ALBERT TAM |
| Grading Pre-Inspection | Cleared | 1/3/2023 | MAHNAZ NOURHASHEMI |
Contact Information
| Architect | Bullock,, Rachel Lane; Lic. No.: C35963 | 741 N OCCIDENTAL BLVD LOS ANGELES, CA 90026 |
| Contractor | Lee Construction Company; Lic. No.: 1072068-B | 21370 NANDINA LANE #203 SANTA CLARITA, CA 91321 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/22/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 5/31/2023 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/1/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 6/2/2023 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 8/1/2023 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/29/2023 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Deputy Reinf. Concrete | 8/31/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 9/8/2023 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/8/2023 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 9/8/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/8/2023 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/8/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 9/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/20/2023 | Corrections Issued | JOSEPH MCGARRY |
| Insulation | 9/25/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/25/2023 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 10/2/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/2/2023 | Partial Inspection | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 10/2/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 11/14/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/14/2023 | Approved | JOSEPH MCGARRY |
| Final | 3/29/2024 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/29/2024 | Approved | ENRIQUE MIRELES |
| Green Building Final | 3/29/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/29/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 3/29/2024 | Approved | ENRIQUE MIRELES |
| Final | 4/5/2024 | Corrections Issued | ROY SPAULDING |
| Final | 9/9/2024 | Corrections Issued | ENRIQUE MIRELES |
| Final | 9/20/2024 | OK to Issue CofO | ENRIQUE MIRELES |